Difference between revisions of "Bioretention: Construction"
Line 74: | Line 74: | ||
'''ESC Inspection and Maintenance (ongoing)'''<br> | '''ESC Inspection and Maintenance (ongoing)'''<br> | ||
=== | ===Excavation and Mass GRading (KM)=== | ||
'''Clearing and Grubbing'''<br> | '''Clearing and Grubbing'''<br> | ||
'''Excavation'''<br> | '''Excavation'''<br> | ||
'''Rough Grade'''<br> | '''Rough Grade'''<br> | ||
'''Verification of Grading/Survey*'''<br> | '''Verification of Grading/Survey*'''<br> | ||
'''Scarification'''<br> | '''Scarification'''<br> | ||
===Backfill Granular and Pipes (JC)=== | ===Backfill Granular and Pipes (JC)=== | ||
'''Geotextile'''<br> | '''Geotextile'''<br> |
Revision as of 13:18, 3 May 2022
This section is also applicable to:
Construction Tasks Table[edit]
Construction Task | Bioretention | Bioswale | Rain garden |
---|---|---|---|
Verification of Siting and LID Design | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Construction Tasks Described[edit]
Pre-Construction (KM)[edit]
Verification of Siting and LID Design
Installation of ESC and Construction Fencing
ESC Inspection and Maintenance (ongoing)
Excavation and Mass GRading (KM)[edit]
Clearing and Grubbing
Excavation
Rough Grade
Verification of Grading/Survey*
Scarification
Backfill Granular and Pipes (JC)[edit]
Geotextile
Impermeable liner
Underdrain
Overflow or Overflow Drain
Monitoring well
Backfill Granular and Pipes (SPC)[edit]
Storage Reservoir
Stone Choker Layer
Curbing
Pre-treatment and Inlet
Soil Media / Filter Media
Finishing Grades: Inlet, Outlet, Biomedia, Plants (SPC)[edit]
Finish Grading
Riprap (Large Stone)
Plant Material Verification and Installation
Mulch Placement
Stabilizing Contributing Drainage Area - Planting Adjacent Vegetation
Finishing Grades: Inlet, Outlet, Biomedia, Plants (JC)[edit]
As-built Survey
Address Deficiencies and Assumption Protocols (JC)[edit]
Permanent Fencing
Identify and Address Deficiencies
Assumption/Certification