==Construction Tasks Table==
{| class="wikitable"
|-
!style="background: darkcyan; color: white"|Construction Stage
!style="background: darkcyan; color: white"|Construction Task
!style="background: white; color: darkcyan"|Permeable Interlocking Concrete Pavers
!style="background: white; color: darkcyan"|Porous Asphalt
!style="background: white; color: darkcyan"|Porous Concrete
|-
| rowspan="4" style="text-align: center; 1style="background:darkcyan; color:white"|Pre-Construction || Verification of Siting and LID Design|| style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|-
| Communication and Utilities Coordination|| style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|-
| Installation of ESC and Construction Fencing|| style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|-
|ESC Inspection and Maintenance (ongoing)||style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|-
| rowspan="5" style="text-align: center;"| Excavation and  <br>  Mass Grading ||Clearing and Grubbing|| style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|-
| Excavation || style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|-
| Subgrade || style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|-
| Verification of Grading/Survey* || style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|-
| rowspan="11" style="text-align: center;"| Backfill Granular,  <br>  Utilities and Pipes ||Geotextile (if applicable) || style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|-
| Impermeable Liner (if applicable) || style="text-align: center;" | x || style="text-align: center;" | x || | 
|-
| Underdrain (if applicable) || style="text-align: center;" | x || style="text-align: center;" | x || | 
|-
| Overflow or Overflow Drain (if applicable)|| style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|-
| Monitoring Well (if applicable)|| style="text-align: center;" | x || style="text-align: center;" | x || | 
|-
| Sub-base Reservoir (if applicable)|| style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|-
| Base Course|| style="text-align: center;" | x || style="text-align: center;" | x || | 
|-
| Filter Layer (if applicable)|| style="text-align: center;" | x || style="text-align: center;" | x || | 
|-
| Bedding layer || style="text-align: center;" | x || style="text-align: center;" | x || | 
|-
| rowspan="7" style="text-align: center;"| Finishing Grades || Placement and Finishing || style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|-
| Paver Installation|| style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|-
| Tamping || style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|-
| Joint Cutting || style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|-
| Joint Aggregate || style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|-
| Curbing (if applicable) || style="text-align: center;" | x || style="text-align: center;" | x || | 
|-
| Stabilizing Contributing Drainage Area || style="text-align: center;" | x || style="text-align: center;" | x || | 
|-
| As-built Survey  || style="text-align: center;" | x || style="text-align: center;" | x || | 
|-
| rowspan="2" style="text-align: center;"| Post-Construction ||Identify and Address Deficiencies || style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|-
| Assumption/Certification Protocols|| style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x
|}

Revision as of 19:37, 21 July 2022

Add here your content!!

Construction Tasks Table[edit]

Construction Stage Construction Task Permeable Interlocking Concrete Pavers Porous Asphalt Porous Concrete
Pre-Construction Verification of Siting and LID Design x x x
Communication and Utilities Coordination x x x
Installation of ESC and Construction Fencing x x x
ESC Inspection and Maintenance (ongoing) x x x
Excavation and
Mass Grading
Clearing and Grubbing x x x
Excavation x x x
Subgrade x x x
Verification of Grading/Survey* x x x
Backfill Granular,
Utilities and Pipes
Geotextile (if applicable) x x x
Impermeable Liner (if applicable) x x
Underdrain (if applicable) x x
Overflow or Overflow Drain (if applicable) x x x
Monitoring Well (if applicable) x x
Sub-base Reservoir (if applicable) x x x
Base Course x x
Filter Layer (if applicable) x x
Bedding layer x x
Finishing Grades Placement and Finishing x x x
Paver Installation x x x
Tamping x x x
Joint Cutting x x x
Joint Aggregate x x x
Curbing (if applicable) x x
Stabilizing Contributing Drainage Area x x
As-built Survey x x
Post-Construction Identify and Address Deficiencies x x x
Assumption/Certification Protocols x x x