Difference between revisions of "Bioretention: Construction"

From LID SWM Planning and Design Guide
Jump to navigation Jump to search
Line 100: Line 100:
===Finishing Grades: Inlet, Outlet, Biomedia, Plants (JC)===
===Finishing Grades: Inlet, Outlet, Biomedia, Plants (JC)===
'''As-built Survey'''<br>
'''As-built Survey'''<br>
===Address Deficiencies and Assumption Protocols===
===Address Deficiencies and Assumption Protocols (JC)===
'''Permanent Fencing'''<br>
'''Permanent Fencing'''<br>
'''Identify and Address Deficiencies'''<br>
'''Identify and Address Deficiencies'''<br>

Revision as of 13:17, 3 May 2022

This section is also applicable to: Bioswale Rain garden

Construction Tasks Table[edit]

Construction Task Bioretention Bioswale Rain garden
Verification of Siting and LID Design Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example
Example Example Example Example

Construction Tasks Described[edit]

Pre-Construction (KM)[edit]

Verification of Siting and LID Design
Installation of ESC and Construction Fencing
ESC Inspection and Maintenance (ongoing)

Construction[edit]

Clearing and Grubbing
Excavation
Rough Grade
Verification of Grading/Survey*
Scarification

Backfill Granular and Pipes (JC)[edit]

Geotextile
Impermeable liner
Underdrain
Overflow or Overflow Drain
Monitoring well

Backfill Granular and Pipes (SPC)[edit]

Storage Reservoir
Stone Choker Layer
Curbing
Pre-treatment and Inlet
Soil Media / Filter Media

Finishing Grades: Inlet, Outlet, Biomedia, Plants (SPC)[edit]

Finish Grading
Riprap (Large Stone)
Plant Material Verification and Installation
Mulch Placement
Stabilizing Contributing Drainage Area - Planting Adjacent Vegetation

Finishing Grades: Inlet, Outlet, Biomedia, Plants (JC)[edit]

As-built Survey

Address Deficiencies and Assumption Protocols (JC)[edit]

Permanent Fencing
Identify and Address Deficiencies
Assumption/Certification

Key Construction Inspection Points[edit]

Inspection Point Timeline[edit]

Construction Mistakes to Avoid[edit]

Construction Certifications Protocols[edit]