Bioretention: Construction

From LID SWM Planning and Design Guide
Jump to navigation Jump to search

This section is also applicable to: Bioswale Rain garden

Construction Tasks Table[edit]

Construction Stage Construction Task Bioretention Bioswale Rain garden
Pre-Construction Verification of Siting and LID Design Example Example Example
Communication and Utilities Coordination Example Example Example
Installation of ESC and Construction Fencing Example Example Example
ESC Inspection and Maintenance (ongoing) Example Example Example
Excavation and
Mass Grading
Clearing and Grubbing Example Example Example
Excavation Example Example Example
Rough Grade Example Example Example
Verification of Grading/Survey* Example Example Example
Scarification (if applicable) Example Example Example
Backfill Granular,
Utilities and Pipes
Geotextile (if applicable) Example Example Example
Impermeable Liner (if applicable) Example Example Example
Underdrain (if applicable) Example Example Example
Overflow or Overflow Drain (if applicable) Example Example Example
Monitoring Well (if applicable) Example Example Example
Clean Out Port Example Example Example
Storage Reservoir Example Example Example
Stone Choker Layer (if applicable) Example Example Example
Curbing (if applicable) Example Example Example
Pre-treatment and Inlet Example Example Example
Soil/Filter Media Example Example Example
Finishing Grades: Inlet,
Outlet, Biomedia and Plants
Finishing Grading Example Example Example
Riprap/Large Stone (if applicable) Example Example Example
Plant Verification and Installation Example Example Example
Mulch Placement Example Example Example
Stabilizing Contributing Drainage Area - Planting Adjacent Vegetation Example Example Example
As-built Survey Example Example Example
Permanent Fencing (if applicable) Example Example Example
Post-Construction Identify and Address Deficiencies Example Example Example
Assumption/Certification Protocols Example Example Example

Construction Tasks Described[edit]

Pre-Construction (KM)[edit]

Verification of Siting and LID Design
Installation of ESC and Construction Fencing
ESC Inspection and Maintenance (ongoing)

Excavation and Mass Grading (KM)[edit]

Clearing and Grubbing
Excavation
Rough Grade
Verification of Grading/Survey*
Scarification

Backfill Granular and Pipes (JC)[edit]

Geotextile
Impermeable liner
Underdrain
Overflow or Overflow Drain
Monitoring well

Backfill Granular and Pipes (SPC)[edit]

Storage Reservoir
Stone Choker Layer
Curbing
It is very important to make sure that the contractor responsible for curb construction understands curb cut designs and elevations. This is often a new technique for contractors and they may not understand the overall concept of water in the gutter line being directed behind the gutter.
Common mistakes to avoid:

  • Elevated curb cuts and reverse slopes (sloping from back of curb towards instead of depressing from gutter line towards the back)
  • Curb cut size (width)
  • Placement of curb cuts on steep slopes or the down slope side of a catchbasin

Pre-treatment and Inlet
Pre-treatment structures are most cost effective when they slow down incoming flows, collect sediment for easy clean out, and release water to the bioretention facility in a non-erosive way. Some pre-treatment structures/strategies include:

  • Vegetation: If sized correctly, it works more effectively in areas with more dispersed flow. However, in concentrated flow and sediment areas it might not be the best option. Sediment removal can be more difficult in areas of dense vegetation. An advantage of using vegetation as pre-treatment is that it can be easily integrated into the landscape design.

Soil Media / Filter Media

Finishing Grades: Inlet, Outlet, Biomedia, Plants (SPC)[edit]

Finish Grading
The finish grading process is another critical handoff moment as a number of elements such as curbs, sidewalks, soils and vegetation start to come together to create the functional and aesthetic value of a site. The same supervision and communication that was put into controlling ESC in earlier stages is also required during finish grading. In many cases, more attention to detail is needed for elements in this phase that will create or not the success of the final product.

Riprap (Large Stone)
Plant Material Verification and Installation

Mulch Placement
Stabilizing Contributing Drainage Area - Planting Adjacent Vegetation

Finishing Grades: Inlet, Outlet, Biomedia, Plants (JC)[edit]

As-built Survey

Address Deficiencies and Assumption Protocols (JC)[edit]

Permanent Fencing
Identify and Address Deficiencies
Assumption/Certification

Key Construction Inspection Points[edit]

Inspection Point Timeline[edit]

Construction Mistakes to Avoid[edit]

Construction Certifications Protocols[edit]