Bioretention: Construction
This section is also applicable to:
Construction Tasks Table[edit]
Construction Task | Bioretention | Bioswale | Rain garden |
---|---|---|---|
Verification of Siting and LID Design | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Example | Example | Example | Example |
Construction Tasks Described[edit]
Pre-Construction (KM)[edit]
Verification of Siting and LID Design
Installation of ESC and Construction Fencing
ESC Inspection and Maintenance (ongoing)
Excavation and Mass GRading (KM)[edit]
Clearing and Grubbing
Excavation
Rough Grade
Verification of Grading/Survey*
Scarification
Backfill Granular and Pipes (JC)[edit]
Geotextile
Impermeable liner
Underdrain
Overflow or Overflow Drain
Monitoring well
Backfill Granular and Pipes (SPC)[edit]
Storage Reservoir
Stone Choker Layer
Curbing
Pre-treatment and Inlet
Soil Media / Filter Media
Finishing Grades: Inlet, Outlet, Biomedia, Plants (SPC)[edit]
Finish Grading
Riprap (Large Stone)
Plant Material Verification and Installation
Mulch Placement
Stabilizing Contributing Drainage Area - Planting Adjacent Vegetation
Finishing Grades: Inlet, Outlet, Biomedia, Plants (JC)[edit]
As-built Survey
Address Deficiencies and Assumption Protocols (JC)[edit]
Permanent Fencing
Identify and Address Deficiencies
Assumption/Certification