Construction Tasks Table[edit]

Construction Stage Construction Task Permeable Interlocking
Concrete Pavers
Porous
Asphalt
Porous
Concrete
Pre-Construction Verification of Siting and LID Design x x x
Communication and Utilities Coordination x x x
Installation of ESC and Construction Fencing x x x
ESC Inspection and Maintenance (ongoing) x x x
Excavation and
Mass Grading
Clearing and Grubbing x x x
Excavation x x x
Subgrade x x x
Verification of Grading/Survey* x x x
Backfill Granular,
Utilities and Pipes
Geotextile (if applicable) x x x
Impermeable Liner (if applicable) x x x
Underdrain (if applicable) x x x
Overflow or Overflow Drain (if applicable) x x x
Monitoring Well (if applicable) x x x
Sub-base Reservoir (if applicable) x x x
Base Course x x x
Filter Layer (if applicable) x x x
Bedding layer x
Finishing Grades Placement and Finishing x x
Paver Installation x
Tamping x x x
Joint Cutting x
Joint Aggregate x
Curbing (if applicable) x x x
Stabilizing Contributing Drainage Area x x x
style="text-align: center;" | x x x
Post-Construction Identify and Address Deficiencies x x x
Assumption/Certification Protocols x x x