Difference between revisions of "Bioretention: Construction"

From LID SWM Planning and Design Guide
Jump to navigation Jump to search
Line 270: Line 270:
===Finishing Grades: Inlet, Outlet, Biomedia, Plants (JC)===
===Finishing Grades: Inlet, Outlet, Biomedia, Plants (JC)===
'''As-built Survey'''<br>
'''As-built Survey'''<br>
Throughout the construction process, it is sometimes necessary to deviate from the intended design of LID features and adapt the design to on-site conditions. The completion of a post-construction as-built survey is a standard operating procedure for engineering projects that captures and changes that were made to the feature’s design during construction.
Survey Steps:
*Use the same datum as the pre-engineering survey
*If a pre-engineering survey is not available, use a reference feature as the datum
*Include data on critical feature elevations and existing utilities, such as:
*Inverts of newly installed pipe
*Vertical and horizontal bends in pipes
*Existing public utilities
*Existing private utilities
*New and existing structures (e.g. catchbasins, manholes, chambers, etc.)
*Identify the type, diameter, and material of exposed utilities
Inspection Points:
*Datum matches the pre-engineering survey or selected reference feature
*Data provided is as-built survey matches the as-built standards of the City
===Address Deficiencies and Assumption Protocols (JC)===
===Address Deficiencies and Assumption Protocols (JC)===
'''Permanent Fencing'''<br>
'''Permanent Fencing'''<br>

Revision as of 13:47, 31 May 2022

This section is also applicable to: Bioswale Rain garden

Construction Tasks Table[edit]

Construction Stage Construction Task Bioretention Bioswale Rain garden
Pre-Construction Verification of Siting and LID Design x x x
Communication and Utilities Coordination x x x
Installation of ESC and Construction Fencing x x x
ESC Inspection and Maintenance (ongoing) x x x
Excavation and
Mass Grading
Clearing and Grubbing x x x
Excavation x x x
Rough Grade x x x
Verification of Grading/Survey* x x x
Scarification (if applicable) x x x
Backfill Granular,
Utilities and Pipes
Geotextile (if applicable) x x x
Impermeable Liner (if applicable) x x
Underdrain (if applicable) x x
Overflow or Overflow Drain (if applicable) x x x
Monitoring Well (if applicable) x x
Clean Out Port x x x
Storage Reservoir x x
Stone Choker Layer (if applicable) x x
Curbing (if applicable) x x
Pre-treatment and Inlet x x x
Soil/Filter Media x x x
Finishing Grades:
Inlet, Outlet,
Biomedia and Plants
Finishing Grading x x x
Riprap/Large Stone (if applicable) x x x
Plant Verification and Installation x x x
Mulch Placement x x x
Stabilizing Contributing Drainage Area -
Planting Adjacent Vegetation
x x x
As-built Survey x x
Permanent Fencing (if applicable) x x
Post-Construction Identify and Address Deficiencies x x x
Assumption/Certification Protocols x x x

Construction Tasks Described[edit]

Pre-Construction (KM)[edit]

Verification of Siting and LID Design
Installation of ESC and Construction Fencing
ESC Inspection and Maintenance (ongoing)

Excavation and Mass Grading (KM)[edit]

Clearing and Grubbing
Excavation
Rough Grade
Verification of Grading/Survey*
Scarification

Backfill Granular and Pipes (JC)[edit]

Geotextile

Geotextiles are filter fabrics that can be installed to separate dissimilar soils and prevent the migration of materials. As such, proper installation of geotextiles is important for ensuring the proper division of materials.


Construction Steps:

  • Roll out fabric on the flattened sub-grade surface
  • Provide a minimum overlap of 300 mm between adjacent lengths of geotextile. If the manufacturer specifies a greater overlap, follow the manufacturer’s specification
  • Fabric should be secured in place with stakes along the edge of the sub-grade surface and where lengths of fabric overlap
  • Provide 500 mm of excess at the ends of each length of fabric
  • Excess material should be folded on top of the infiltration medium/choker course once installed
  • Provide cuts for trees where appropriate


Key Inspection Points:

  • Inspect the geotextile to make sure it is clean and free of damage
  • Ensure that the geotextile delivered to the site matches the design specifications and is approved by the engineer prior to installation
  • Check that sufficient overlap is provided between lengths of fabric
  • Confirm that geotextiles have been applied as per the manufacturer’s guidelines
  • Confirm that structural considerations for geotextiles that are applied adjacent to infrastructure


Mistakes to Avoid:

  • Wrinkles in the fabric – follow the manufacturer’s procedure for installation to ensure geotextiles lie smooth on sub-grade
  • Unnecessary application of geotextile – mixing of media is negligible where structural loads are not expected, so geotextile does not need to be applied. Also geotextiles should not be used where root growth is encouraged to penetrate different layers of media


For more information on geotextiles, see the page on geotextiles.


Impermeable liner
Underdrains are pipes that can be included to collect subsurface water. Their design is determined by the drainage requirements of the feature.


Construction Steps:

  • Install the underdrain to grade with a consistent slope of 0.5% to 1.0%
  • Connect overflow risers with single-elbowed ‘y’ connections or 45° elbows
  • Situate maintenance risers where siltation is expected in drain lines (such as at junctions or where grade and direction changes occur)
  • Mark the locations of risers
  • Use video inspections to confirm that the interior of the underdrain remains free of debris after construction


Key Inspection Points:

  • Size, type, and material of the underdrain conforms to the design specifications
  • Underdrain is perforated prior to arrival on-site
  • Drain material is resistant to UV radiation and any chemicals in the soil and groundwater
  • Clean-outs are positioned correctly and spaced appropriately for the size of the underdrain
  • Any manual perforations are approved by the engineer
  • Pipe grade matches design specifications
  • Tie-in locations to municipal sewers meet City specifications


Mistakes to Avoid:

  • Incorrect overflow risers – ensure single-elbowed ‘y’ connections or 45° elbows are used for overflow risers instead of ‘T’ connections
  • Incorrect drain size – confirm underdrain has an internal diameter greater than or equal to 200 mm to reduce freezing and allow cleaning and camera inspections
  • Potential for clogging – Ensure gravel coverings have not been included with the underdrain


For more information on the design of under-drains, see the page on under-drains.


Underdrain
Impermeable liners can be applied when LID features are not intended to infiltrate runoff into the underlying soil. Where building foundations that are adjacent to the LID feature are not waterproofed, liners can be used to protect neighbouring infrastructure.


Construction Steps:

  • Compact 30 – 50 mm of sand over the soil onto which the membrane will be installed to protect against punctures. Alternatively, a geotextile can be used in the place of sand
  • Place lengths of liner on the bed of the facility as per the manufacturer’s specifications
  • Provide 150 mm of overlap between adjacent lengths of liner
  • Secure liner in-place and bond together the overlapping portions of liner as specified by the manufacturer
  • Where pipes provide drainage from the practice, a flange should be sealed to the pipe and liner.
  • Compact sand or apply cushion fabric on top of the liner to protect against punctures


Key Inspection Points:

  • Liner is confirmed to match design specifications
  • Liner installation conforms to manufacturer’s specifications
  • Minimum overlap with
  • Need for impermeable liner is confirmed through field verification of setbacks to adjacent infrastructure
  • Sand and/or geotextile are applied on both sides of the liner to protect against punctures
  • Lengths of liner are bonded together to ensure protection against groundwater contamination


For more information on impermeable liners, see the page on liners.


Overflow or Overflow Drain
Overflows are features of inline facilities and convey larger storm events out of the LID feature.


Construction Steps:

  • Connect the overflow drain to the under-drain
  • Install overflow pit to grade at the location specified in the contract documents
  • Fit a metal, domed grate to the overflow


Key Inspection Points:

  • Overflow drain matches design specifications
  • Overflow pit is positioned at the maximum water surface elevation of the practice, as per the contract documents
  • Sufficient freeboard is provided between the overflow and inlet such that the inlet is not inundated by design storm flows
  • Overflow grate matches design specifications
  • Overflow grates that are located in high-traffic areas are screwed on or equipped with locks


Mistakes to Avoid:

  • Backflows – ensure that backflows are avoided by confirming that inlet and overflow elevations match design specifications with surveys
  • Incorrect sequencing – install overflow drain prior to backfilling with granular material and engineered soil
  • Incorrect grate material – avoid using plastic overflow grates due to breakages and UV degradation

For more information on overflow drains, see the page on overflows.


Monitoring well
Monitoring wells are important for sampling procedures and ensuring that bioretention features are performing as intended.


Construction Steps:

  • Anchor the perforated pipe to the bottom of the LID feature
  • Install a lockable cap to the top of the standpipe to protect against vandalism


Key Inspection Points:

  • Pipe is perforated, rigid, and matches design specifications
  • Well is installed according to contract documents
  • Geotextile sock is wrapped around the perforated portion of the well


Mistakes to Avoid:

  • Incorrect sequencing – ensure that standpipe is installed prior to backfilling with granular material


For more information on monitoring wells, see the page on monitoring wells.

Backfill Granular and Pipes (SPC)[edit]

Storage Reservoir
Stone Choker Layer
Curbing
It is very important to make sure that the contractor responsible for curb construction understands curb cut designs and elevations. This is often a new technique for contractors and they may not understand the overall concept of water in the gutter line being directed behind the gutter.
Common mistakes to avoid:

  • Elevated curb cuts and reverse slopes (sloping from back of curb towards instead of depressing from gutter line towards the back)
  • Curb cut size (width)
  • Placement of curb cuts on steep slopes or the down slope side of a catchbasin

Pre-treatment and Inlet
Pre-treatment structures are most cost effective when they slow down incoming flows, collect sediment for easy clean out, and release water to the bioretention facility in a non-erosive way. Some pre-treatment structures/strategies include:

  • Vegetation: If sized correctly, it works more effectively in areas with more dispersed flow. However, in concentrated flow and sediment areas it might not be the best option. Sediment removal can be more difficult in areas of dense vegetation. An advantage of using vegetation as pre-treatment is that it can be easily integrated into the landscape design.
  • Concrete curbing

Items to ensure during construction:

  • Verify that’s correct pretreatment device (jelly fish, vegetation, curbing, etc.)
  • Correct size and location
  • Correct elevation and footing
  • Tied into the curb? or could happen before the curbing?
  • Does it work?

For more information about pre-treatment strategies and their design, visit these page: Pretreatment and Pretreatment features

Soil Media / Filter Media

For small LID facilities, apply soil media in 150-300 mm lifts until desired top elevation of bioretention, bioswale or rain garden area is achieved. Thoroughly wet each lift before adding the next and wail until water has drainer through the soil before adding the next lift. Avoid manual or machine compaction. If possible, equipment should not be operated within the infiltration practice. If required, allow soil to dry before equipment is allowed back into the practice.

For large LID facilities, slinger trucks are recommended for spreading soil in even layers and reducing the need to move soil media manually or by backhoe. If possible, equipment should not be operated within the infiltration practice. If necessary, appropriate low ground pressure rated equipment can enter after at least 45 cm of bioretention, bioswale or rain garden soil is installed and has properly dried.

Soil/filter media’s design parameters and assumptions should be confirmed through in-situ permeability testing (e.g., permeameter measurements to determine hydraulic conductivity). Results of permeability testing should be reviewed by the designer and, if required, changes to the LID design may be needed.

All exposed soil areas that are not being actively worked must have temporary erosion protection or permanent cover within 7 days for slopes 3:1 or greater and 14 days for slopes 3:1 or greater and 14 days for slopes 3:1 or flatter. This should apply to all exposed soil areas year-round and until the site is stabilized.

Upon material arrival to the site, make sure to conduct:

  • Chain of custody
  • Visual inspection
  • Grab a sample, ribbon test

Finishing Grades: Inlet, Outlet, Biomedia, Plants (SPC)[edit]

Finish Grading
The finish grading process is another critical handoff moment as a number of elements such as curbs, sidewalks, soils and vegetation start to come together to create the functional and aesthetic value of a site. The same supervision and communication that was put into controlling ESC in earlier stages is also required during finish grading. In many cases, more attention to detail is needed for elements in this phase that will create or not the success of the final product.

Riprap (Large Stone)
Plant Material Verification and Installation

Mulch Placement
Stabilizing Contributing Drainage Area - Planting Adjacent Vegetation

Finishing Grades: Inlet, Outlet, Biomedia, Plants (JC)[edit]

As-built Survey
Throughout the construction process, it is sometimes necessary to deviate from the intended design of LID features and adapt the design to on-site conditions. The completion of a post-construction as-built survey is a standard operating procedure for engineering projects that captures and changes that were made to the feature’s design during construction.


Survey Steps:

  • Use the same datum as the pre-engineering survey
  • If a pre-engineering survey is not available, use a reference feature as the datum
  • Include data on critical feature elevations and existing utilities, such as:
  • Inverts of newly installed pipe
  • Vertical and horizontal bends in pipes
  • Existing public utilities
  • Existing private utilities
  • New and existing structures (e.g. catchbasins, manholes, chambers, etc.)
  • Identify the type, diameter, and material of exposed utilities


Inspection Points:

  • Datum matches the pre-engineering survey or selected reference feature
  • Data provided is as-built survey matches the as-built standards of the City

Address Deficiencies and Assumption Protocols (JC)[edit]

Permanent Fencing
Identify and Address Deficiencies
Assumption/Certification

Key Construction Inspection Points[edit]

Inspection Point Timeline[edit]

Construction Mistakes to Avoid[edit]

Construction Certifications Protocols[edit]