Difference between revisions of "As-built surveys"

From LID SWM Planning and Design Guide
Jump to navigation Jump to search
(Created page with "Throughout the construction process, it is sometimes necessary to deviate from the intended design of LID features and adapt the design to on-site conditions. The completion of a post-construction as-built survey is a standard operating procedure for engineering projects that captures any changes made to the feature’s design during construction.<sb> Survey Steps: #Use the same datum as the pre-engineering survey #If a pre-engineering survey is not available, use a ref...")
(No difference)

Revision as of 20:02, 19 July 2022

Throughout the construction process, it is sometimes necessary to deviate from the intended design of LID features and adapt the design to on-site conditions. The completion of a post-construction as-built survey is a standard operating procedure for engineering projects that captures any changes made to the feature’s design during construction.<sb>

Survey Steps:

  1. Use the same datum as the pre-engineering survey
  2. If a pre-engineering survey is not available, use a reference feature as the datum
  3. Include data on critical feature elevations and existing utilities, such as:
  • Inverts of newly installed pipe
  • Vertical and horizontal bends in pipes
  • Existing public utilities
  • Existing private utilities
  • New and existing structures (e.g., catchbasins, manholes, chambers, etc.)
  1. Identify the type, diameter, and material of exposed utilities

Inspection Points:

  • Datum matches the pre-engineering survey or selected reference feature
  • Data provided in as-built survey matches the as-built standards of the local municipality