Difference between revisions of "Construction: clearing and grubbing"

From LID SWM Planning and Design Guide
Jump to navigation Jump to search
(Created page with "====Clearing and grubbing==== Clearing and grubbing is the stripping of vegetation and topsoil prior to excavation and rough grading within designated areas. '''Construction steps''' #Clear trees, large shrubs, stumps, etc. (grubbing). #Use appropriately sized machinery (e.g. a mini-excavator) to strip sod and ground-level vegetation (clearing). #Stockpile materials within designated areas if necessary. If the materials are being hauled offsite, stripped materials idea...")
(No difference)

Revision as of 17:26, 20 July 2022

Clearing and grubbing[edit]

Clearing and grubbing is the stripping of vegetation and topsoil prior to excavation and rough grading within designated areas.

Construction steps

  1. Clear trees, large shrubs, stumps, etc. (grubbing).
  2. Use appropriately sized machinery (e.g. a mini-excavator) to strip sod and ground-level vegetation (clearing).
  3. Stockpile materials within designated areas if necessary. If the materials are being hauled offsite, stripped materials ideally would go straight into the back of a dump truck.
  4. Secure stockpiles with appropriate ESC measures if the material must be stored before hauling offsite or will be reused.

Key inspection points

  • Structural ESC measures are in place before clearing and grubbing begin.
  • Natural heritage features, including trees, and construction limits are clearly marked and respected by the contractor.
  • Contractor cleared and grubbed only within designated areas and according to the phasing plan.

Mistakes to avoid

  • Clearing more area than is needed
  • Insufficient marking of areas to be protected
  • Stockpiling materials without ESC controls or for extended periods of time
  • Leaving heavy equipment in the facility’s footprint
  • Making excessive passes with heavy equipment in the LID practice’s footprint without scouring soil afterward