Difference between revisions of "Construction"
Kyle menken (talk | contribs) m |
Kyle menken (talk | contribs) m |
||
Line 19: | Line 19: | ||
===Pre-construction=== | ===Pre-construction=== | ||
Pre-construction activities set the stage for the successful construction of an LID practice. The pre-construction stage | Pre-construction activities set the stage for the successful construction of '''an LID''' practice. The pre-construction page gives guidance on: | ||
*design verification and site walk-through | |||
*LID construction notes | |||
*tendering and contract | |||
*communication, inspection plan, and utilities coordination | |||
*Erosion and sediment control measures | |||
*Mobilization, access, staging, and perimeter controls | |||
The pre-construction stage should begin by field-verifying the design when it is at the 90% completion stage and conducting a site walk-through. | |||
===Excavation and grading=== | ===Excavation and grading=== | ||
===Backfill granular, utilities, and pipes=== | ===Backfill granular, utilities, and pipes=== | ||
Sub-surface layers | |||
===Finishing grades and surface layer=== | ===Finishing grades and surface layer=== | ||
Where things get a little tricky | |||
===Post-construction=== | ===Post-construction=== | ||
If you assume the works too early, u make and ass out of me. | |||
==LID practice pages== | ==LID practice pages== |
Revision as of 18:03, 2 August 2022
Overview[edit]
- Importance of construction inspections
- Contractor familiarity
- What you can expect from STEP guidance: practical advice, specific to LID, practical advice on how to ensure successful construction
Construction stages[edit]
STEP divides the construction process for LID practices into five over-arching stages:
- Pre-construction
- Excavation and grading
- Backfill granular, utilities, and pipes
- Finishing grades: inlet, outlet, and surface layer
- Post-construction
Stages 1-3 and 5 of the LID construction process are fundamentally similar for all surface-level LID types. To illustrate, STEP's recommended processes for excavation do not differ depending on the practice type. Excavation is excavation, whether it is for a bioretention garden or a permeable paver parking lot. On the other hand, stage 4 sub-tasks will vary substantially from practice to practice, as do some sub-tasks in stage 3. The following paragraphs give a brief explanation of each over-arching stage.
Pre-construction[edit]
Pre-construction activities set the stage for the successful construction of an LID practice. The pre-construction page gives guidance on:
- design verification and site walk-through
- LID construction notes
- tendering and contract
- communication, inspection plan, and utilities coordination
- Erosion and sediment control measures
- Mobilization, access, staging, and perimeter controls
The pre-construction stage should begin by field-verifying the design when it is at the 90% completion stage and conducting a site walk-through.
Excavation and grading[edit]
Backfill granular, utilities, and pipes[edit]
Sub-surface layers
Finishing grades and surface layer[edit]
Where things get a little tricky
Post-construction[edit]