Difference between revisions of "Construction"

From LID SWM Planning and Design Guide
Jump to navigation Jump to search
m
m
Line 25: Line 25:
*communication, inspection plan, and utilities coordination
*communication, inspection plan, and utilities coordination
*Erosion and sediment control measures
*Erosion and sediment control measures
*Mobilization, access, staging, and perimeter controls
*mobilization, access, staging, and perimeter controls
 
 
 
The pre-construction stage should begin by field-verifying the design when it is at the 90% completion stage and conducting a site walk-through.   
 
===Excavation and grading===  
===Excavation and grading===  
Excavation and grading are necessary for installing LID practices with sub-surface components, re-grading land to hold more water, and re-routing overland flow routes into the LID practice in question. The excavation and grading page gives guidance on:
*clearing and grubbing
*excavation and rough grade
*final excavated grade and verification


===Backfill granular, utilities, and pipes===
Many LID practices rely on sub-surface features--storage reservoirs, liners, underdrains, etc.--to function. The '''backfill granular, utilities, and pipes / sub-surface components''' page gives guidance on:
*geotextile (if applicable)
*underdrain
*impermeable liners
*overflow
*monitoring wells
*storage reservoir
*stone choker layer
*curbing
*pre-treatment and inlet


===Backfill granular, utilities, and pipes===
===Finishing grades and surface layer installation===
Sub-surface layers


===Finishing grades and surface layer===
*soil media installation and soil amendment
Where things get a little tricky
*finish grading
*large stone and riprap
*plant verification and installation
*mulch placement
*stabilizing contributing drainage area and planting adjacent vegetation
*as-built survey


===Post-construction===
===Post-construction===
Line 43: Line 59:


==LID practice pages==
==LID practice pages==
Each construction page listed below :)
8008

Revision as of 19:02, 2 August 2022

Overview[edit]

  • Importance of construction inspections
  • Contractor familiarity
  • What you can expect from STEP guidance: practical advice, specific to LID, practical advice on how to ensure successful construction

Construction stages[edit]

STEP divides the construction process for LID practices into five over-arching stages:

  1. Pre-construction
  2. Excavation and grading
  3. Backfill granular, utilities, and pipes
  4. Finishing grades: inlet, outlet, and surface layer
  5. Post-construction

Stages 1-3 and 5 of the LID construction process are fundamentally similar for all surface-level LID types. To illustrate, STEP's recommended processes for excavation do not differ depending on the practice type. Excavation is excavation, whether it is for a bioretention garden or a permeable paver parking lot. On the other hand, stage 4 sub-tasks will vary substantially from practice to practice, as do some sub-tasks in stage 3. The following paragraphs give a brief explanation of each over-arching stage.

Pre-construction[edit]

Pre-construction activities set the stage for the successful construction of an LID practice. The pre-construction page gives guidance on:

  • design verification and site walk-through
  • LID construction notes
  • tendering and contract
  • communication, inspection plan, and utilities coordination
  • Erosion and sediment control measures
  • mobilization, access, staging, and perimeter controls

Excavation and grading[edit]

Excavation and grading are necessary for installing LID practices with sub-surface components, re-grading land to hold more water, and re-routing overland flow routes into the LID practice in question. The excavation and grading page gives guidance on:

  • clearing and grubbing
  • excavation and rough grade
  • final excavated grade and verification

Backfill granular, utilities, and pipes[edit]

Many LID practices rely on sub-surface features--storage reservoirs, liners, underdrains, etc.--to function. The backfill granular, utilities, and pipes / sub-surface components page gives guidance on:

  • geotextile (if applicable)
  • underdrain
  • impermeable liners
  • overflow
  • monitoring wells
  • storage reservoir
  • stone choker layer
  • curbing
  • pre-treatment and inlet

Finishing grades and surface layer installation[edit]

  • soil media installation and soil amendment
  • finish grading
  • large stone and riprap
  • plant verification and installation
  • mulch placement
  • stabilizing contributing drainage area and planting adjacent vegetation
  • as-built survey

Post-construction[edit]

If you assume the works too early, u make and ass out of me.

LID practice pages[edit]

Each construction page listed below :)

8008