Difference between revisions of "Construction"
Kyle menken (talk | contribs) m |
Kyle menken (talk | contribs) m |
||
Line 9: | Line 9: | ||
STEP divides the construction process for LID practices into five over-arching stages: | STEP divides the construction process for LID practices into five over-arching stages: | ||
#Pre-construction | #[[Pre-construction|pre-construction]] | ||
#Excavation and grading | #Excavation and grading | ||
#Backfill granular, utilities, and pipes | #Backfill granular, utilities, and pipes |
Revision as of 19:08, 2 August 2022
Overview[edit]
- Importance of construction inspections
- Contractor familiarity
- What you can expect from STEP guidance: practical advice, specific to LID, practical advice on how to ensure successful construction
Construction stages[edit]
STEP divides the construction process for LID practices into five over-arching stages:
- pre-construction
- Excavation and grading
- Backfill granular, utilities, and pipes
- Finishing grades: inlet, outlet, and surface layer
- Post-construction
Stages 1-3 and 5 of the LID construction process are fundamentally similar for all surface-level LID types. To illustrate, STEP's recommended processes for excavation do not differ depending on the practice type. Excavation is excavation, whether it is for a bioretention garden or a permeable paver parking lot. On the other hand, stage 4 sub-tasks will vary substantially from practice to practice, as do some sub-tasks in stage 3. The following paragraphs give a brief explanation of each over-arching stage.
Pre-construction[edit]
Pre-construction activities set the stage for the successful construction of an LID practice. The pre-construction page gives guidance on:
- design verification and site walk-through
- LID construction notes
- tendering and contract
- communication, inspection plan, and utilities coordination
- Erosion and sediment control measures
- mobilization, access, staging, and perimeter controls
Excavation and grading[edit]
Excavation and grading are necessary for installing LID practices with sub-surface components, re-grading land to hold more water, and re-routing overland flow routes into the LID practice in question. The excavation and grading page gives guidance on:
- clearing and grubbing
- excavation and rough grade
- final excavated grade and verification
Backfill granular, utilities, and pipes[edit]
Many LID practices rely on sub-surface features--storage reservoirs, liners, underdrains, etc.--to function. The backfill granular, utilities, and pipes / sub-surface components page gives guidance on:
- geotextile (if applicable)
- underdrain
- impermeable liners
- overflow
- monitoring wells
- storage reservoir
- stone choker layer
- curbing
- pre-treatment and inlet
Finishing grades and surface layer installation[edit]
- soil media installation and soil amendment
- finish grading
- large stone and riprap
- plant verification and installation
- mulch placement
- stabilizing contributing drainage area and planting adjacent vegetation
- as-built survey
Post-construction[edit]
If you assume the works too early, u make and ass out of me.
LID practice pages[edit]
Each construction page listed below :)
8008