Difference between revisions of "As-built surveys"
Jump to navigation
Jump to search
JamesCowan (talk | contribs) |
JamesCowan (talk | contribs) |
||
(16 intermediate revisions by 2 users not shown) | |||
Line 1: | Line 1: | ||
Throughout the construction process, it is sometimes necessary to deviate from the intended design of LID features and adapt the design to on-site conditions. The completion of a post-construction as-built survey is a standard operating procedure for engineering projects that captures any changes made to the feature’s design during construction.< | Throughout the construction process, it is sometimes necessary to deviate from the intended design of LID features and adapt the design to on-site conditions. The completion of a post-construction as-built survey is a standard operating procedure for engineering projects that captures any changes made to the feature’s design during construction. For an example of municipal standards for as-built surveys, refer to the City of Toronto's [https://www.toronto.ca/wp-content/uploads/2017/11/98c7-ecs-specs-surveys-engsrv_survey_standards_for_consultant.pdf Engineering Survey Standards for Consultants]<ref>City of Toronto. 2021. Engineering Survey Standards for Consultants. https://www.toronto.ca/wp-content/uploads/2017/11/98c7-ecs-specs-surveys-engsrv_survey_standards_for_consultant.pdf</ref> | ||
Survey Steps: | '''Survey Steps:''' | ||
#Use the same datum as the pre-engineering survey | #Use the same datum as the pre-engineering survey. | ||
#If a pre-engineering survey is not available, use a reference feature as the datum | #If a pre-engineering survey is not available, use a reference feature as the datum. | ||
#Identify the type, diameter, and material of exposed utilities | #Identify the type, diameter, and material of exposed utilities. | ||
#Include data on critical feature elevations and existing utilities, such as: | #Include data on critical feature elevations and existing utilities, such as: | ||
*Inverts of newly installed pipe | #*Inverts of newly installed pipe | ||
*Vertical and horizontal bends in pipes | #*Vertical and horizontal bends in pipes | ||
*Existing public utilities | #*Existing public utilities | ||
*Existing private utilities | #*Existing private utilities | ||
*New and existing structures (e.g., catchbasins, manholes, chambers, etc.) | #*New and existing structures (e.g., catchbasins, manholes, chambers, etc.) | ||
Inspection Points: | '''Inspection Points:''' | ||
*Datum matches the pre-engineering survey or selected reference feature | *Datum matches the pre-engineering survey or selected reference feature. | ||
*Data provided in as-built survey matches the as-built standards of the local municipality | *Data provided in as-built survey matches the as-built standards of the local municipality. |
Latest revision as of 17:38, 30 September 2022
Throughout the construction process, it is sometimes necessary to deviate from the intended design of LID features and adapt the design to on-site conditions. The completion of a post-construction as-built survey is a standard operating procedure for engineering projects that captures any changes made to the feature’s design during construction. For an example of municipal standards for as-built surveys, refer to the City of Toronto's Engineering Survey Standards for Consultants[1]
Survey Steps:
- Use the same datum as the pre-engineering survey.
- If a pre-engineering survey is not available, use a reference feature as the datum.
- Identify the type, diameter, and material of exposed utilities.
- Include data on critical feature elevations and existing utilities, such as:
- Inverts of newly installed pipe
- Vertical and horizontal bends in pipes
- Existing public utilities
- Existing private utilities
- New and existing structures (e.g., catchbasins, manholes, chambers, etc.)
Inspection Points:
- Datum matches the pre-engineering survey or selected reference feature.
- Data provided in as-built survey matches the as-built standards of the local municipality.
- ↑ City of Toronto. 2021. Engineering Survey Standards for Consultants. https://www.toronto.ca/wp-content/uploads/2017/11/98c7-ecs-specs-surveys-engsrv_survey_standards_for_consultant.pdf