Difference between revisions of "Bioretention: Sizing and modeling"
Jenny Hill (talk | contribs) |
Jenny Hill (talk | contribs) |
||
Line 31: | Line 31: | ||
The following equations assume that infiltration occurs primarily through the base of the facility. | The following equations assume that infiltration occurs primarily through the base of the facility. | ||
They may be applied for any shape and size of infiltration facility. | They may be easily applied for any shape and size of infiltration facility, in which the reservoir storage is mostly in an aggregate. | ||
* Note: For systems that have significant storage in clear open chambers, an effective porosity value (''n''') may be estimated for the whole installation and applied to these calculations. The effective porosity will vary according to the geometry of the storage chambers and advice should be sought from product manufacturers. Permit applications should include information which has been used to calculate ''n'''. | |||
To calculate the required depth, where the area of the facility is constrained: | To calculate the required depth, where the area of the facility is constrained: |
Revision as of 21:47, 18 August 2017
Before beginning the sizing calculations most of the following parameters must be known or estimated. The exceptions are the depth (d) and Permeable area (P), as only one of these is required to find the other. Note that some of these parameters are limited:
- The maximum total depth will be limited by construction practices i.e. not usually > 2 m.
- The maximum total depth may be limited by the conditions underground e.g. the groundwater or underlying geology/infrastructure.
- The minimum total depth may be limited by the need to support vegetation i.e. not < 0.6 m.
- The area P for a green roofs, absorbent landscapes and permeable paving may be very similar or equal to the catchment area, so that the I/P ratio is close to 1.
- Infiltration trenches, chambers and bioretention cells have a maximum recommended I/P ratio of 20.
Symbol | Units | Parameter |
---|---|---|
D | hrs | Duration of design storm (for MOECC volume based caclulations set to 1) |
i | mm/hr | Intensity of design storm (for MOECC volume based calculations use whole storm depth (link to map)) |
q | mm/hr | Infiltration coefficient, calculated from measured infiltration rate and applied safety factor |
n | - | Porosity, as measured (or default to 0.35) |
I | m2 | Impermeable area i.e. catchment |
d | m | depth of infiltration facility or BMP |
P | m2 | Permeable area i.e. footprint area of the facility or BMP |
The following equations assume that infiltration occurs primarily through the base of the facility. They may be easily applied for any shape and size of infiltration facility, in which the reservoir storage is mostly in an aggregate.
- Note: For systems that have significant storage in clear open chambers, an effective porosity value (n) may be estimated for the whole installation and applied to these calculations. The effective porosity will vary according to the geometry of the storage chambers and advice should be sought from product manufacturers. Permit applications should include information which has been used to calculate n.
To calculate the required depth, where the area of the facility is constrained:
To calculate the require facility area or footprint where the depth is constrained:
This spreadsheet tool has been set up to perform either of the above calculations.
Download .xlsx calculation tool
To calculate the time (t) to fully drain the facility:
Accounting for lateral infiltration[edit]
For some geometries (e.g. particularly deep facilities or linear facilities), it may be preferred to also account for lateral infiltration.
The 3 dimensional equations make use of the hydraulic radius (P/x), where x is the perimeter (m) of the facility.
Maximizing the perimeter of the facility directs designers towards longer, linear shapes such as infiltration trenches and bioswales.
To calculate the required depth:
Where and
The rearrangement to calculate the required footprint area of the facility for a given depth is not available at this time. Elegant submissions are invited.
To calculate the time (t) to fully drain the facility: