Difference between revisions of "As-built surveys"
Jump to navigation
Jump to search
JamesCowan (talk | contribs) |
JamesCowan (talk | contribs) |
||
Line 1: | Line 1: | ||
Throughout the construction process, it is sometimes necessary to deviate from the intended design of LID features and adapt the design to on-site conditions. The completion of a post-construction as-built survey is a standard operating procedure for engineering projects that captures any changes made to the feature’s design during construction.<br> | Throughout the construction process, it is sometimes necessary to deviate from the intended design of LID features and adapt the design to on-site conditions. The completion of a post-construction as-built survey is a standard operating procedure for engineering projects that captures any changes made to the feature’s design during construction.<br> | ||
Survey Steps:<br> | '''Survey Steps:'''<br> | ||
#Use the same datum as the pre-engineering survey | #Use the same datum as the pre-engineering survey. | ||
#If a pre-engineering survey is not available, use a reference feature as the datum | #If a pre-engineering survey is not available, use a reference feature as the datum. | ||
#Identify the type, diameter, and material of exposed utilities | #Identify the type, diameter, and material of exposed utilities. | ||
#Include data on critical feature elevations and existing utilities, such as: | #Include data on critical feature elevations and existing utilities, such as: | ||
***Inverts of newly installed pipe | ***Inverts of newly installed pipe | ||
Line 12: | Line 12: | ||
***New and existing structures (e.g., catchbasins, manholes, chambers, etc.)<br> | ***New and existing structures (e.g., catchbasins, manholes, chambers, etc.)<br> | ||
Inspection Points:<br> | '''Inspection Points:'''<br> | ||
*Datum matches the pre-engineering survey or selected reference feature | *Datum matches the pre-engineering survey or selected reference feature. | ||
*Data provided in as-built survey matches the as-built standards of the local municipality<br> | *Data provided in as-built survey matches the as-built standards of the local municipality.<br> |
Revision as of 01:50, 21 July 2022
Throughout the construction process, it is sometimes necessary to deviate from the intended design of LID features and adapt the design to on-site conditions. The completion of a post-construction as-built survey is a standard operating procedure for engineering projects that captures any changes made to the feature’s design during construction.
Survey Steps:
- Use the same datum as the pre-engineering survey.
- If a pre-engineering survey is not available, use a reference feature as the datum.
- Identify the type, diameter, and material of exposed utilities.
- Include data on critical feature elevations and existing utilities, such as:
- Inverts of newly installed pipe
- Vertical and horizontal bends in pipes
- Existing public utilities
- Existing private utilities
- New and existing structures (e.g., catchbasins, manholes, chambers, etc.)
Inspection Points:
- Datum matches the pre-engineering survey or selected reference feature.
- Data provided in as-built survey matches the as-built standards of the local municipality.