Kyle menken (talk | contribs) (Created page with "====Clearing and grubbing==== Clearing and grubbing is the stripping of vegetation and topsoil prior to excavation and rough grading within designated areas. '''Construction steps''' #Clear trees, large shrubs, stumps, etc. (grubbing). #Use appropriately sized machinery (e.g. a mini-excavator) to strip sod and ground-level vegetation (clearing). #Stockpile materials within designated areas if necessary. If the materials are being hauled offsite, stripped materials idea...") |
Kyle menken (talk | contribs) |
||
Line 1: | Line 1: | ||
===Clearing and grubbing=== | |||
Clearing and grubbing is the stripping of vegetation and topsoil prior to excavation and rough grading within designated areas. | Clearing and grubbing is the stripping of vegetation and topsoil prior to excavation and rough grading within designated areas. | ||
Revision as of 17:39, 20 July 2022
Clearing and grubbing[edit]
Clearing and grubbing is the stripping of vegetation and topsoil prior to excavation and rough grading within designated areas.
Construction steps
- Clear trees, large shrubs, stumps, etc. (grubbing).
- Use appropriately sized machinery (e.g. a mini-excavator) to strip sod and ground-level vegetation (clearing).
- Stockpile materials within designated areas if necessary. If the materials are being hauled offsite, stripped materials ideally would go straight into the back of a dump truck.
- Secure stockpiles with appropriate ESC measures if the material must be stored before hauling offsite or will be reused.
Key inspection points
- Structural ESC measures are in place before clearing and grubbing begin.
- Natural heritage features, including trees, and construction limits are clearly marked and respected by the contractor.
- Contractor cleared and grubbed only within designated areas and according to the phasing plan.
Mistakes to avoid
- Clearing more area than is needed
- Insufficient marking of areas to be protected
- Stockpiling materials without ESC controls or for extended periods of time
- Leaving heavy equipment in the facility’s footprint
- Making excessive passes with heavy equipment in the LID practice’s footprint without scouring soil afterward