Kyle menken (talk | contribs) (Created page with "===Final excavated grade and verification=== LID designs typically have very specific grading requirements. Verifying depths and slopes is critical for optimal performance of the facility. For example, if the design calls for a channel with a 1 % slope, the channel may not function as designed if it has a 2 % slope instead. Similarly, if the designs call for 1 metre of excavation from grade and only 90 cm are excavated, it will not have enough storage space to meet the d...") |
|||
Line 1: | Line 1: | ||
=== | ===Excavation and mass grading: final excavated grade and verification=== | ||
LID designs typically have very specific grading requirements. Verifying depths and slopes is critical for optimal performance of the facility. For example, if the design calls for a channel with a 1 % slope, the channel may not function as designed if it has a 2 % slope instead. Similarly, if the designs call for 1 metre of excavation from grade and only 90 cm are excavated, it will not have enough storage space to meet the design criteria. <br/> | LID designs typically have very specific grading requirements. Verifying depths and slopes is critical for optimal performance of the facility. For example, if the design calls for a channel with a 1 % slope, the channel may not function as designed if it has a 2 % slope instead. Similarly, if the designs call for 1 metre of excavation from grade and only 90 cm are excavated, it will not have enough storage space to meet the design criteria. <br/> | ||
'''Construction steps''' | '''Construction steps''' |
Revision as of 17:09, 22 July 2022
Excavation and mass grading: final excavated grade and verification[edit]
LID designs typically have very specific grading requirements. Verifying depths and slopes is critical for optimal performance of the facility. For example, if the design calls for a channel with a 1 % slope, the channel may not function as designed if it has a 2 % slope instead. Similarly, if the designs call for 1 metre of excavation from grade and only 90 cm are excavated, it will not have enough storage space to meet the design criteria.
Construction steps
- Excavate from the rough grade to the finish grade using appropriate equipment. This is often done with hand tools.
- Confirm excavation depths and slopes using appropriate equipment (transit levels, global navigation satellite systems, etc.)
Key inspection points
- Confirm final excavated depths and slopes.
Mistakes to avoid
- “Eye-balling” depths and slopes