Difference between revisions of "As-built surveys"
Jump to navigation
Jump to search
JamesCowan (talk | contribs) |
JamesCowan (talk | contribs) |
||
Line 15: | Line 15: | ||
'''Inspection Points:''' | '''Inspection Points:''' | ||
*Datum matches the pre-engineering survey or selected reference feature. | *Datum matches the pre-engineering survey or selected reference feature. | ||
*Data provided in as-built survey matches the as-built standards of the local municipality. | *Data provided in as-built survey matches the as-built standards of the local municipality. | ||
<references/> | <references/> |
Revision as of 14:27, 21 July 2022
As-built Surveys[edit]
Throughout the construction process, it is sometimes necessary to deviate from the intended design of LID features and adapt the design to on-site conditions. The completion of a post-construction as-built survey is a standard operating procedure for engineering projects that captures any changes made to the feature’s design during construction.
Survey Steps:
- Use the same datum as the pre-engineering survey.
- If a pre-engineering survey is not available, use a reference feature as the datum.
- Identify the type, diameter, and material of exposed utilities.
- Include data on critical feature elevations and existing utilities, such as:[1]
- Inverts of newly installed pipe
- Vertical and horizontal bends in pipes
- Existing public utilities
- Existing private utilities
- New and existing structures (e.g., catchbasins, manholes, chambers, etc.)
Inspection Points:
- Datum matches the pre-engineering survey or selected reference feature.
- Data provided in as-built survey matches the as-built standards of the local municipality.