Difference between revisions of "Bioretention: Construction checklist"
Jenny Hill (talk | contribs) |
Jenny Hill (talk | contribs) |
||
Line 14: | Line 14: | ||
|style="width:30px"| | |style="width:30px"| | ||
|Gravel for the underdrain should be clean and washed; no fines should be present in the material | |Gravel for the underdrain should be clean and washed; no fines should be present in the material | ||
|- | |||
|| | || | ||
|Underdrain pipe material should be perforated and of the correct size (when specified in design) | |Underdrain pipe material should be perforated and of the correct size (when specified in design) | ||
|- | |||
|| | || | ||
|A cap should be placed on the upstream (but not the downstream) end of the underdrain (when specified in design) | |A cap should be placed on the upstream (but not the downstream) end of the underdrain (when specified in design) | ||
|- | |||
|| | || | ||
|Biomedia should be tested to confirm that it meets specifications | |Biomedia should be tested to confirm that it meets specifications | ||
|- | |||
|| | || | ||
|Mulch composition should be correct | |Mulch composition should be correct |
Revision as of 00:02, 5 September 2017
Common construction pitfalls can be avoided with careful construction supervision that focuses on the following aspects:
Erosion and Sediment Control | |
---|---|
Bioretention locations should be blocked from construction traffic and should not be used for erosion and sediment control | |
Proper erosion and sediment controls should be in place for the drainage area | |
Materials | |
Gravel for the underdrain should be clean and washed; no fines should be present in the material | |
Underdrain pipe material should be perforated and of the correct size (when specified in design) | |
A cap should be placed on the upstream (but not the downstream) end of the underdrain (when specified in design) | |
Biomedia should be tested to confirm that it meets specifications | |
Mulch composition should be correct |
Elevations
Depth of the gravel and invert of the underdrain
Inverts for inflow and outflow points
Filter depth? after biomedia is placed
Ponding depth provided between the surface of the filter bed and the overflow structure
Mulch depth
Landscaping and Stabilization
Correct vegetation should be planted
Pretreatment area should be stabilized
Drainage area should be stabilized prior to directing water to the bioretention
The following items should be checked after the first rainfall event, and adjustments should be made as necessary:
Outfall protection/energy dissipation at concentrated inflow should be stable
Flow should not concentrate and should spread evenly over the filter bed
Ponded water at the surface of the bioretenton facility must drain within 24 hours of the end of the storm event.
The biomedia should fully drain within a maximum period of 72 hours
Excessive sediment accumulation should not be present