#Cut and stabilize channels and slopes.
#Cut and stabilize channels and slopes.
#Excavate the LID feature from the outside-in whenever possible. A standard excavator (10-45 tons) has a longer reach than mini (<6 tons) or midi excavators (6-10 tons) and can be the best choice despite its weight, since it may not need to enter into the facility’s footprint to complete the job. However, a mini excavator would be the best choice if entry into the LID feature’s footprint is necessary.
#Excavate the LID feature from the outside-in whenever possible. A standard excavator (10-45 tons) has a longer reach than mini (<6 tons) or midi excavators (6-10 tons) and can be the best choice despite its weight, since it may not need to enter into the facility’s footprint to complete the job. However, a mini excavator would be the best choice if entry into the LID feature’s footprint is necessary.
#Excavate to within 100 mm of the final grade  
#Excavate to within 100 mm of the final grade.
#Check grades with appropriate equipment (transit levels, etc.)
#Check grades with appropriate equipment (transit levels, etc.).
#Stockpile materials in a designated area if it must be stored before hauling
#Stockpile materials in a designated area if it must be stored before hauling.
#When backfill materials are ready, excavate remaining 100 mm to final grade and scouring bottom if applicable using toothed bucket.   
#When backfill materials are ready, excavate remaining 100 mm to final grade and scouring bottom if applicable using toothed bucket.   
'''Key inspection points:'''