*Confirm the limit of excavation.
*Confirm the limit of excavation.
*Use of excavation equipment specified in the contract, in the required manner (from the outside in, with a mini excavator, etc.).
*Use of excavation equipment specified in the contract, in the required manner (from the outside in, with a mini excavator, etc.).
*Confirm excavated rough grade and final grade prior to backfilling using survey equipment
*Confirm excavated rough grade and final grade prior to backfilling using survey equipment.
*Use of toothed bucket and scouring the bottom of practice if applicable
*Use of toothed bucket and scouring the bottom of practice if applicable.
*If appropriate, measure compaction using a cone penetration test or a cone penetrometer  
*If appropriate, measure compaction using a cone penetration test or a cone penetrometer .
*If appropriate, field verify infiltration rates at excavated bottom of practice using Guelph permeameter or double ring infiltrometer
*If appropriate, field verify infiltration rates at excavated bottom of practice using Guelph permeameter or double ring infiltrometer.
'''Mistakes to avoid:'''
'''Mistakes to avoid:'''
*Making too many passes with heavy machinery within the LID footprint.
*Making too many passes with heavy machinery within the LID footprint.
*Leaving heavy machinery within the LID’s footprint (for breaks, lunch, overnight, etc.)
*Leaving heavy machinery within the LID’s footprint (for breaks, lunch, overnight, etc.).
*Using the wrong equipment
*Using the wrong equipment.
*Over excavating
*Over excavating.
*Smearing the bottom of the practice with the bucket, which can compact native soils
*Smearing the bottom of the practice with the bucket, which can compact native soils.


==Final excavated grade and verification==
==Final excavated grade and verification==