As-built surveys

From LID SWM Planning and Design Guide
Revision as of 20:03, 19 July 2022 by JamesCowan (talk | contribs)
Jump to navigation Jump to search

Throughout the construction process, it is sometimes necessary to deviate from the intended design of LID features and adapt the design to on-site conditions. The completion of a post-construction as-built survey is a standard operating procedure for engineering projects that captures any changes made to the feature’s design during construction.<sb>

Survey Steps:

  1. Use the same datum as the pre-engineering survey
  2. If a pre-engineering survey is not available, use a reference feature as the datum
  3. Identify the type, diameter, and material of exposed utilities
  4. Include data on critical feature elevations and existing utilities, such as:
  • Inverts of newly installed pipe
  • Vertical and horizontal bends in pipes
  • Existing public utilities
  • Existing private utilities
  • New and existing structures (e.g., catchbasins, manholes, chambers, etc.)<sb>

Inspection Points:<sb>

  • Datum matches the pre-engineering survey or selected reference feature
  • Data provided in as-built survey matches the as-built standards of the local municipality<sb>