Changes

Jump to navigation Jump to search
m
no edit summary
Line 1: Line 1:
{| class="wikitable floatright" style="width: 200px"
|+ Be sure to verify all design changes
|-
|[[File:T-junction_photo.jpg|200px]][[File:Y-junction design detail.png|200px]]
|-
|A simple departure from the design—installing a T-junction (top) in place of a Y-junction (below) would have made it extremely difficult or impossible to inspect this underdrain and flush it out. (Image sources: CVC)
|-
|}
</br>
After securing a contractor, a pre-construction meeting between the project manager, project engineer, and contractor will facilitate an efficient job site and reduce the potential for miscommunication. These meetings should cover:
After securing a contractor, a pre-construction meeting between the project manager, project engineer, and contractor will facilitate an efficient job site and reduce the potential for miscommunication. These meetings should cover:


Line 10: Line 19:
*ownership and assumption protocols
*ownership and assumption protocols
*project inspection plan
*project inspection plan
*verification processes for field changes to the design and material substitutions
The table below expands upon the bullets above and provides helpful guidance on communication topics at the pre-construction meeting. Given the lead-up time needed for testing requirements of specified materials, these discussions should occur soon after the contract is awarded, ideally 2 months prior to project construction. 


The table below expands upon the bullets above and provides helpful guidance on communication topics at the pre-construction meeting. Given the lead-up time needed for testing requirements of specified materials, these discussions should occur soon after the contract is awarded, ideally 2 months prior to project construction.   


{|class="wikitable"
{|class="wikitable"
Line 19: Line 31:
!Guidance
!Guidance
|-
|-
|LID design details and construction notes||-Provide overview of LID design, ideally through a design brief.
|'''LID design details and construction notes'''||
-Discuss LID design details and construction notes, and ensure details and notes are understood by all parties involved.  
*Provide overview of LID design, ideally through a design brief.
 
*Discuss LID design details and construction notes, and ensure details and notes are understood by all parties involved.  
-Discuss project phasing and general timeliness.
*Discuss project phasing and general timeliness.
 
|-
|-
 
|'''Material specifications, inspections, and chain-of-custody'''||
|Material specifications, inspections, and chain-of-custody||-Material substitutions must be confirmed by the project engineer.  
*Material substitutions must be confirmed by the project engineer.  
-Material testing requirements and their timelines must be understood by all parties, including who is responsible for testing.  
*Material testing requirements and their timelines must be understood by all parties, including who is responsible for testing.  
-Material acceptance protocols, with chain of custody, should be understood by all parties, including who is responsible if the material fails.
*Material acceptance protocols, with chain of custody, should be understood by all parties, including who is responsible if the material fails.
 
*[[Bioretention: Filter media|Biomedia]] manufacturing and testing should start prior to construction, ideally 2 months in advance.
-Biomedia manufacturing and testing should start prior to construction, ideally 2 months in advance.
 
|-
|-
 
|'''Access routes and storage areas'''||
|Access routes and storage areas||-Discuss access to the site along with material and equipment storage with the contractor.
*Discuss access to the site along with material and equipment storage with the contractor.
-Material storage should be downstream of LID features.
*Material storage should be downstream of LID features.
 
*Heavy equipment routes should be agreed on to minimize impact to the LID feature and protected areas.
-Heavy equipment routes should be agreed on to minimize impact to the LID feature and protected areas.
 
|-
|-
 
|'''Protection of LID practices during construction: phasing, ESC, and perimeter controls'''||
|Protection of LID practices during construction: phasing, ESC, and perimeter controls||-Review and discuss the ESC plan.
*Review and discuss the ESC plan.
-Discuss frequency of ESC inspection, protocols for repair and replacement and, parties responsible.
*Discuss frequency of ESC inspection, protocols for repair and replacement, and parties responsible.
-Discuss communication protocols for sediment contamination.
*Discuss communication protocols for sediment contamination.
 
*Discuss rehabilitation protocols for sediment contamination and parties responsible.
-Discuss rehabilitation protocols for sediment contamination and parties responsible.
 
|-
|-
 
|'''Equipment requirements and recommendations'''||
|Equipment requirements and recommendations||-Wide track, low-ground pressure vehicles are recommended to minimize compaction.
*Wide track, low-ground pressure vehicles are recommended to minimize compaction.
-Excavation should occur from outside of LID feature whenever possible.  See Excavation.  
*Excavation should occur from outside of LID feature whenever possible.  See Excavation.  
-Gravel and biomedia should be installed by a slinger truck outside of practice whenever possible.
*Gravel and biomedia should be installed by a slinger truck outside of practice whenever possible.
 
*Avoid heavy machinery within LID footprint whenever possible.  
-Avoid heavy machinery within LID footprint whenever possible.  
 
|-
|-
 
|'''Verification of field changes'''||
|Verification of field changes||-The project engineer must verify all field changes to materials and design.  
*The project engineer must verify all field changes to materials and design.  
 
*In the design engineer’s absence, the project manager should verify field changes.  
-In the design engineer’s absence, the project manager should verify field changes.  
 
|-
|-
 
|'''Plant establishment and warranty-period maintenance'''||
|Plant establishment and warranty-period maintenance||-Discuss planting timelines at the pre-construction meeting.
*Discuss [[Plant selection|planting]] timelines at the pre-construction meeting.
-Avoid planting in the summer months (June, July and August). Fall planting is the ideal scenario.
*Avoid planting in the summer months (June, July and August). Fall planting is the ideal scenario.
-Plants will require regular maintenance (irrigation and weeding) to ensure establishment, especially over the first year.
*Plants will require regular maintenance (irrigation and weeding) to ensure establishment, especially over the first year.
-Ensure that plant maintenance and its frequency is understood and which party is responsible.
*Ensure that plant maintenance and its frequency is understood by responsible parties.
 
*Plant deficiencies should be addressed prior to warranty period initiating.
-Plant deficiencies should be addressed prior to warranty period initiating.
 
|-
|-
 
|'''Ownership and assumption protocols'''||
|Ownership and assumption protocols||-Discuss how testing will confirm LID  practice functionality according to assumption protocols.
*Discuss how testing will confirm LID  practice functionality according to assumption protocols.
 
|-
|-
 
|'''Project inspection plan'''||
|Project inspection plan||-Project inspection plan should be detailed and understood by all parties involved.
*Project inspection plan should be detailed and understood by all parties.
 
*Sign off by all parties involved on photos, video, and social media post may be required.  
-Sign off by all parties involved on photos, video, and social media post may be required.  
 
|}
|}


=====Inspection plan=====
=====Inspection plan=====


Ideally, inspections should be continuous as the work progresses. If this isn’t possible, critical inspection points are:
The [[inspection and maintenance]] page gives detailed guidance on how to conduct construction inspections for LID practices. Generally, construction inspections should be continuous as the work progresses. If this isn’t possible, critical inspection points are:
*site preparation
*site preparation
*excavation
*excavation
722

edits

Navigation menu