Line 297: Line 297:
Table below provides guidance on rehabilitation and repair work specific to vegetated/grass filter strips and soil amendments organized according to BMP component.
Table below provides guidance on rehabilitation and repair work specific to vegetated/grass filter strips and soil amendments organized according to BMP component.
   
   
[[File:Levelspread.jpg|thumb|430px|This clever design incorporates a level spreading device after a [[curb cut]] has narrowed the flow path. This kind of treatment train approach would provide an opportunity to provide [[pretreatment]] at the point of concentration. This repair helps to limit the potential of erosion occurring within the feature. Photo credit: [https://www.pca.state.mn.us/featured/when-it-rains-it-flows (MPCA, 204)]<ref>Minnesota Pollution Control Agency. 2014. When it rains, it flows. 6 May 2014. Accessed 156 July 2022. https://www.pca.state.mn.us/featured/when-it-rains-it-flows</ref>]]   
[[File:Levelspread.jpg|thumb|440px|This clever design incorporates a level spreading device after a [[curb cut]] has narrowed the flow path. This kind of treatment train approach would provide an opportunity to provide [[pretreatment]] at the point of concentration. This repair helps to limit the potential of erosion occurring within the feature. Photo credit: [https://www.pca.state.mn.us/featured/when-it-rains-it-flows (MPCA, 204)]<ref>Minnesota Pollution Control Agency. 2014. When it rains, it flows. 6 May 2014. Accessed 156 July 2022. https://www.pca.state.mn.us/featured/when-it-rains-it-flows</ref>]]   




Line 367: Line 367:
#Maintenance and rehabilitation costs over a 25 year time period are estimated to be 3.52 to 5.42 times the original construction cost, for the Minimum Recommended and High Frequency maintenance scenarios respectively.
#Maintenance and rehabilitation costs over a 25 year time period are estimated to be 3.52 to 5.42 times the original construction cost, for the Minimum Recommended and High Frequency maintenance scenarios respectively.
#Maintenance and rehabilitation costs over a 50 year time period are estimated to be 6.16 and 9.57 times  the original construction cost for the Minimum Recommended and High Frequency maintenance scenarios respectively.</small>
#Maintenance and rehabilitation costs over a 50 year time period are estimated to be 6.16 and 9.57 times  the original construction cost for the Minimum Recommended and High Frequency maintenance scenarios respectively.</small>
==Inspection Field Data Sheet==
Feel free to '''download''' (downward facing arrow on the top righthand side) and '''print''' (Pinter emoticon on top right hand side) the following [[Vegetated filter strips]] and [[Absorbent landscapes|Soil amendments]] Inspection Field Data Form developed by TRCA, STEP and its partners for the [https://sustainabletechnologies.ca/app/uploads/2016/08/LID-IM-Guide-2016-1.pdf Low Impact Development Stormwater Management Practice Inspection and Maintenance Guide]<ref>STEP. 2016. Low Impact Development Stormwater Management Practice Inspection and Maintenance Guide. https://sustainabletechnologies.ca/app/uploads/2016/08/LID-IM-Guide-2016-1.pdf</ref>.
The 6 page document prompts users to fill out details previously mentioned above on this page in other sections about various zones associated with [[[Vegetated Filter strips]] and [[Absorbent landscapes|Soil amendments]]  features (i.e. inlets, perimeter of the feature, filter bed, outlets, etc.) and describe why each area is a pass or fail, and if remediate action is required and under what timeframe it would be completed by. Furthermore, the forms prompt the reviewer to determine what type of inspection is being conducted for the feature in question: Construction (C), Routine Operation (RO), Maintenance Verification (MV), or Performance Verification (PV). <br>
<br>
[[File:Filterstrip toronto 2021.JPG|thumb|340px|Example of a plan drawing and appropriate construction specifications for [[Vegetated filter strips]] designed and implemented within Toronto's, municipal bounds (City of Toronto, 2021)<ref>City of Toronto. 2021. Construction Specifications and Drawings for Green Infrastructure. T-850.151 Vegetated Filter Strip – Section. Developed by: Engineering and Construction Services. https://www.toronto.ca/wp-content/uploads/2021/08/9646-ecs-specs-gi-dwgs-T-850.151-Rev0-Sep2021.pdf</ref>]]
<pdf width="900" height="800">File:Fitler strips inspection sheet.pdf</pdf>