Line 533: |
Line 533: |
| #Determine the drainage time from the water level measurements | | #Determine the drainage time from the water level measurements |
| #Calculate the infiltration rate based on water level measurements once flow from the subdrain has stopped as the change in storage volume over time divided by the infiltration area. | | #Calculate the infiltration rate based on water level measurements once flow from the subdrain has stopped as the change in storage volume over time divided by the infiltration area. |
| #If more than 13 m<sup>3</sup> of water (i.e., the typical capacity of water tanker trucks) is needed to fill the sub-surface water storage reservoir, a fire hydrant will need to be used as the water source.<br> | | #If more than 13 m<sup>3</sup> of water (i.e., the typical capacity of water tanker trucks) is needed to fill the sub-surface water storage reservoir, a fire hydrant will need to be used as the water source. |
| <br> | | <br> |
|
| |
|
Line 539: |
Line 539: |
| *Mean values for drainage time and infiltration rate should be calculated and compared to design specifications or regulatory criteria to determine if the BMP is draining at an acceptable rate. | | *Mean values for drainage time and infiltration rate should be calculated and compared to design specifications or regulatory criteria to determine if the BMP is draining at an acceptable rate. |
| *Alternatively, a simulated storm event test can be performed, using the stepwise procedure described above. | | *Alternatively, a simulated storm event test can be performed, using the stepwise procedure described above. |
| | |
| | ===Water Treatment Performance Evaluations=== |
| | When the objectives of BMP inspection include determining if the BMP is providing a minimum level of water treatment performance, design of the continuous monitoring program needs considerable thought. Table 8.10 describes some key considerations in program design. |
| | |
| | |
| | Key considerations in designing continuous monitoring programs for water treatment |
| | evaluation. |
| | |
| | |
|
| |
|
| For further information regarding natural and simulated storm event testing, acceptance criteria per LID BMP type and associated testing tools and protocols scroll down to the embedded 2016 guide below. | | For further information regarding natural and simulated storm event testing, acceptance criteria per LID BMP type and associated testing tools and protocols scroll down to the embedded 2016 guide below. |