Jenny Hill (talk | contribs) (Created page with "To size a bioretention facility using this page, the design infiltration rate (q' in mm/hr, after correction) of the native underlying soils must estimated, and the maxi...") |
Jenny Hill (talk | contribs) m (→Step 1) |
||
Line 2: | Line 2: | ||
If the space on the ground is the tighter constraint to design, try this article on [[sizing bioretention for space]]. | If the space on the ground is the tighter constraint to design, try this article on [[sizing bioretention for space]]. | ||
==Step 1== | |||
The bioretention facility will comprise three vertical zones: | The bioretention facility will comprise three vertical zones: | ||
#a 'bowl' permitting water to pond occasionally, | #a 'bowl' permitting water to pond occasionally, |
Revision as of 14:04, 6 November 2017
To size a bioretention facility using this page, the design infiltration rate (q' in mm/hr, after correction) of the native underlying soils must estimated, and the maximum available excavation depth (d in m) is the primary constraint to sizing.
If the space on the ground is the tighter constraint to design, try this article on sizing bioretention for space.
Step 1[edit]
The bioretention facility will comprise three vertical zones:
- a 'bowl' permitting water to pond occasionally,
- a layer of filter media to support plant growth, and
- a reservoir of stone to store and facilitate infiltration of additional water.
Firstly, all three zones will be sized together within the limited depth to find the footprint area of the whole bioretention facility. To do this the mean void ratio is estimated to be 0.35. To calculate the require facility area or footprint where the depth is constrained:
Where:
- D = Duration of design storm in hrs
- i = Intensity of design storm in mm/hr
- q' = Design infiltration rate in mm/hr
- VR = Void ratio (porosity), as measured (or default to 0.35 for all aggregates)
- R = Ratio of catchment area (Ac) to BMP footprint area (Ap) syn. I/P ratio.
- Ap = Area of the infiltration practice in m2
- d = Depth of infiltration practice in m.