Difference between revisions of "Permeable pavements: Construction"
Jump to navigation
Jump to search
Line 7: | Line 7: | ||
!style="background: darkcyan; color: white"|Construction Task | !style="background: darkcyan; color: white"|Construction Task | ||
!style="background: white; color: darkcyan"|Permeable Interlocking <br> Concrete Pavers | !style="background: white; color: darkcyan"|Permeable Interlocking <br> Concrete Pavers | ||
!style="background: white; color: darkcyan"|Porous Asphalt | !style="background: white; color: darkcyan"|Porous<br> Asphalt | ||
!style="background: white; color: darkcyan"|Porous Concrete | !style="background: white; color: darkcyan"|Porous<br> Concrete | ||
|- | |- | ||
| rowspan="4" style="text-align: center; 1style="background:darkcyan; color:white"|Pre-Construction || Verification of Siting and LID Design|| style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x | | rowspan="4" style="text-align: center; 1style="background:darkcyan; color:white"|Pre-Construction || Verification of Siting and LID Design|| style="text-align: center;" | x || style="text-align: center;" | x || style="text-align: center;" | x |
Revision as of 19:40, 21 July 2022
Add here your content!!
Construction Tasks Table[edit]
Construction Stage | Construction Task | Permeable Interlocking Concrete Pavers |
Porous Asphalt |
Porous Concrete |
---|---|---|---|---|
Pre-Construction | Verification of Siting and LID Design | x | x | x |
Communication and Utilities Coordination | x | x | x | |
Installation of ESC and Construction Fencing | x | x | x | |
ESC Inspection and Maintenance (ongoing) | x | x | x | |
Excavation and Mass Grading |
Clearing and Grubbing | x | x | x |
Excavation | x | x | x | |
Subgrade | x | x | x | |
Verification of Grading/Survey* | x | x | x | |
Backfill Granular, Utilities and Pipes |
Geotextile (if applicable) | x | x | x |
Impermeable Liner (if applicable) | x | x | ||
Underdrain (if applicable) | x | x | ||
Overflow or Overflow Drain (if applicable) | x | x | x | |
Monitoring Well (if applicable) | x | x | ||
Sub-base Reservoir (if applicable) | x | x | x | |
Base Course | x | x | ||
Filter Layer (if applicable) | x | x | ||
Bedding layer | x | x | ||
Finishing Grades | Placement and Finishing | x | x | x |
Paver Installation | x | x | x | |
Tamping | x | x | x | |
Joint Cutting | x | x | x | |
Joint Aggregate | x | x | x | |
Curbing (if applicable) | x | x | ||
Stabilizing Contributing Drainage Area | x | x | ||
As-built Survey | x | x | ||
Post-Construction | Identify and Address Deficiencies | x | x | x |
Assumption/Certification Protocols | x | x | x |