Line 24: Line 24:

{{:Overflow: Installation}}
{{:Overflow: Installation}}
[[Overflow|Overflows]] are features of inline facilities and convey larger storm events out of the LID feature.
'''Construction Steps:'''
#Connect the overflow drain to the underdrain.
#Fit a metal, domed grate to the overflow.
#Install overflow pit to grade at the location specified in the contract documents.
'''Key Inspection Points:'''
*Overflow drain matches design specifications.
*Overflow pit is positioned at the maximum water surface elevation of the practice, as per the contract documents.
*Sufficient freeboard is provided between the overflow and inlet such that the inlet is not inundated by design storm flows.
*Overflow grate matches design specifications.
*Overflow grates located in high-traffic areas are screwed on or equipped with locks.
'''Mistakes to Avoid:'''
*Backflows – ensure that backflows are avoided by confirming that inlet and overflow elevations match design specifications with surveys.
*Incorrect sequencing – install overflow drain prior to backfilling with granular material and engineered soil.
*Incorrect grate material – avoid using plastic overflow grates due to breakages and UV degradation.
<gallery mode="packed" widths=300px heights=300px>
overflow-pipe-install.jpg | Overflow pipe installed to an underdrain T-connection.
overflow-plastic-cap.jpg | Overflow installed with a plastic cap. Note that the use of plastic grates is discouraged.
</gallery>