| ==Pretreatment and inlet== | | ==Pretreatment and inlet== |
| {{:Construction: pretreatment and inlet}} | | {{:Construction: pretreatment and inlet}} |
|
| |
| Pre-treatment structures are most cost effective when they slow down incoming flows, collect sediment for easy clean out, and slowly release water to the bioretention facility mitigating erosion. [[Pretreatment]] structures/strategies can include [[curb cuts]], [[Aggregates]], proprietary devices like filters or hydrodynamic separators, vegetation, concrete sumps, membrane filters, overland flow sumps, etc.
| |
|
| |
| '''Construction Steps:'''
| |
| *Installation of pre-treatment features will vary based upon type. Similarly, installation timeline will range with type and could occur at excavation and mass grading, curb work or at finishing grade. Given pre-treatment features are typically integrated with the LID inlet coordination amongst multiple sub-contractors is sometime needed. The following details steps for various pre-treatment types:
| |
| *Vegetation: Follow the guidance shown below in the section “Plant Material Verification and Installation”
| |
| *Curbing: Follow the guidance shown above in the section “Curbing”.
| |
| *Aggregate: Follow the guidance shown above in the section “Stone reservoir”.
| |
| <gallery mode="packed" widths=300px heights=300px>
| |
| IMG_0891.JPG|Aggregate material (rock) installed as the inlet and pre-treatment device in the rain garden at Glendale P.S. in Brampton, ON. The runoff comes from a vegetated swale into the inlet, conveying it into the rain garden.
| |
| IMG_0744.JPG|Aggregate material (rock) installed as the inlet and pre-treatment device in the rain garden at Glendale P.S. in Brampton, ON. The runoff comes from a vegetated swale into the inlet, conveying it into the rain garden.
| |
| IMG_0788-1.JPG|Aggregate material (rock) installed as the inlet and pre-treatment device in the rain garden at Glendale P.S. in Brampton, ON. The runoff comes from a vegetated swale into the inlet, conveying it into the rain garden.
| |
| </gallery>
| |
|
| |
| [[Category:Gallery]]
| |
|
| |
| *Proprietary pre-treatment device:
| |
| #Excavate and prepare base for proprietary pre-treatment device according to design.
| |
| #Install proprietary pre-treatment device according manufacturer directions.
| |
| #Manufacturer representative may need to confirm proper installation and functioning through approved testing and inspection. <br>
| |
|
| |
| <gallery mode="packed" widths=275px heights=275px>
| |
| P1160102.JPG|Installation of Jellyfish filter and sorbtive media vault at the IMAX bioswale project in Mississauga, ON.
| |
| P1160117.JPG|Installation of Jellyfish filter and sorbtive media vault at the IMAX bioswale project in Mississauga, ON.
| |
| P1160121.JPG|Installation of Jellyfish filter and sorbtive media vault at the IMAX bioswale project in Mississauga, ON.
| |
|
| |
| </gallery>
| |
|
| |
| [[Category:Gallery]]
| |
|
| |
| '''Key Inspection Points:'''
| |
| *Verify that the correct pre-treatment device (jellyfish filter, vegetation, curbing, etc.) is being installed.
| |
| *Verify that all components of the pre-treatment device are installed
| |
| *Verify correct size and location of pre-treatment device.
| |
| *Verify correct elevation, slope, and footing according to design
| |
| *Is it tied into the curb, downspout, or other inlet? Or could happen before the curbing?
| |
| *Wet weather performance check:
| |
| **Does it work?
| |
| **Is water entering the LID facility properly?
| |
| **Is sediment and debris accumulating?
| |
| **Is it dissipating erosive forces?
| |
|
| |
| '''Mistakes to Avoid:'''
| |
| *Pre-treatment component parts are missing
| |
| *Grading/elevation errors that deviates from design
| |
| **Incorrect pipe inverts causing short circuiting
| |
| **Insufficient grade drop or slope into pre-treatment to ensure positive flow of water
| |
| **Improper grading from pre-treatment to LID feature inhibiting positive flow
| |
| **Insufficient sump depth to account for sediment and debris accumulation
| |
| *Using wrong concrete forms if concrete curbs are part of pre-treatment.
| |
|
| |
| For more information about pre-treatment strategies and their design, visit these page: [[Pretreatment]] and [[Pretreatment features]].
| |
|
| |
|
| ==References== | | ==References== |
| <references/> | | <references/> |