Monitoring wells: Installation

From LID SWM Planning and Design Guide
Jump to navigation Jump to search
Monitoring well stack installed next to underdrain within the LID practice.

Monitoring wells allow for measurement of water levels in the sub-surface components of LID practices. They are important for sampling procedures and ensuring that the LID feature are performing as intended.

Construction Steps:

  1. Install a cap stand at the required elevation to anchor the monitoring well.
  2. Wrap the perforated pipe with a geotextile sock (to prevent migration of soil into the well).
  3. Anchor the perforated pipe to the bottom of the LID feature.
  4. Install a lockable cap to the top of the standpipe to protect against vandalism.
  5. Install monitoring equipment (e.g., a level logger) if required.

Key Inspection Points:

  • Pipe is perforated, rigid, and matches design specifications.
  • Well is installed according to contract documents.
  • Geotextile sock is wrapped around the perforated portion of the well.

Mistakes to Avoid:

  • Incorrect sequencing – ensure that standpipe is installed prior to backfilling with granular material.