Difference between revisions of "Permeable pavements: Construction"

From LID SWM Planning and Design Guide
Jump to navigation Jump to search
Line 6: Line 6:
!style="background: darkcyan; color: white"|Construction Stage
!style="background: darkcyan; color: white"|Construction Stage
!style="background: darkcyan; color: white"|Construction Task
!style="background: darkcyan; color: white"|Construction Task
!style="background: white; color: darkcyan"|Permeable Interlocking Concrete Pavers
!style="background: white; color: darkcyan"|Permeable Interlocking <br> Concrete Pavers
!style="background: white; color: darkcyan"|Porous Asphalt
!style="background: white; color: darkcyan"|Porous Asphalt
!style="background: white; color: darkcyan"|Porous Concrete
!style="background: white; color: darkcyan"|Porous Concrete

Revision as of 19:40, 21 July 2022

Add here your content!!

Construction Tasks Table[edit]

Construction Stage Construction Task Permeable Interlocking
Concrete Pavers
Porous Asphalt Porous Concrete
Pre-Construction Verification of Siting and LID Design x x x
Communication and Utilities Coordination x x x
Installation of ESC and Construction Fencing x x x
ESC Inspection and Maintenance (ongoing) x x x
Excavation and
Mass Grading
Clearing and Grubbing x x x
Excavation x x x
Subgrade x x x
Verification of Grading/Survey* x x x
Backfill Granular,
Utilities and Pipes
Geotextile (if applicable) x x x
Impermeable Liner (if applicable) x x
Underdrain (if applicable) x x
Overflow or Overflow Drain (if applicable) x x x
Monitoring Well (if applicable) x x
Sub-base Reservoir (if applicable) x x x
Base Course x x
Filter Layer (if applicable) x x
Bedding layer x x
Finishing Grades Placement and Finishing x x x
Paver Installation x x x
Tamping x x x
Joint Cutting x x x
Joint Aggregate x x x
Curbing (if applicable) x x
Stabilizing Contributing Drainage Area x x
As-built Survey x x
Post-Construction Identify and Address Deficiencies x x x
Assumption/Certification Protocols x x x