A [[bioretention]] cell with footprint of 30 x 10 m is planned to received runoff from adjacent roadways and parking facilities. The design includes 600 mm depth of filter medium, 75 mm wood based mulch, and ponding of 300 mm. Two underdrain pipes will be embedded at the base of the storage reservoir. These will connect together and then have an upturn within a manhole at the downstream end to prevent discharge until the head of water reaches the top of the storage reservoir within the cell. The lab test for the filter medium state that it has a hydraulic conductivity of 80 mm/hr. The maximum flow through the medium will be calculated and a comparison made with the maximum flow through the pipe to see....:
A [[bioretention]] cell with footprint of 30 x 10 m is planned to received runoff from adjacent roadways and parking facilities. The design includes 600 mm depth of filter medium, 75 mm wood based mulch, and ponding of 300 mm. Two underdrain pipes will be embedded at the base of the storage reservoir. These will connect together and then have an upturn within a manhole at the downstream end to prevent discharge until the head of water reaches the top of the storage reservoir within the cell. The lab test for the filter medium state that it has a hydraulic conductivity of 80 mm/hr. The maximum flow through the medium will be calculated and a comparison made with the maximum flow through the pipe to see....:
<math>Q_{max, m}=\frac{80 mm/hr\times 300\ m^{2}\times \left (\frac{0.975\ m}{0.6\ m}  \right )}{3600\ s/hr}=10.8\ L/s</math>
<math>Q_{max, m}=\frac{80 mm/hr\times 300\ m^{2}\times \left (\frac{0.975\ m}{0.6\ m}  \right )\times 2}{3600\ s/hr}=21.6\ L/s</math>

Navigation menu