[[Overflow|Overflows]] are features of inline facilities and convey larger storm events out of the LID feature.<br>
[[Overflow|Overflows]] are features of inline facilities and convey larger storm events out of the LID feature.<br>


Construction Steps:<br>
'''Construction Steps:'''<br>
#Connect the overflow drain to the underdrain.
#Connect the overflow drain to the underdrain.
#Install overflow pit to grade at the location specified in the contract documents.
#Install overflow pit to grade at the location specified in the contract documents.
#Fit a metal, domed grate to the overflow.<br>
#Fit a metal, domed grate to the overflow.<br>


Key Inspection Points:<br>
'''Key Inspection Points:'''<br>
*Overflow drain matches design specifications.
*Overflow drain matches design specifications.
*Overflow pit is positioned at the maximum water surface elevation of the practice, as per the contract documents.
*Overflow pit is positioned at the maximum water surface elevation of the practice, as per the contract documents.
Line 13: Line 13:
*Overflow grates located in high-traffic areas are screwed on or equipped with locks.<br>
*Overflow grates located in high-traffic areas are screwed on or equipped with locks.<br>


Mistakes to Avoid:<br>
'''Mistakes to Avoid:'''<br>
*Backflows – ensure that backflows are avoided by confirming that inlet and overflow elevations match design specifications with surveys.
*Backflows – ensure that backflows are avoided by confirming that inlet and overflow elevations match design specifications with surveys.
*Incorrect sequencing – install overflow drain prior to backfilling with granular material and engineered soil.
*Incorrect sequencing – install overflow drain prior to backfilling with granular material and engineered soil.