| [[Overflow|Overflows]] are features of inline facilities and convey larger storm events out of the LID feature.<br> | | [[Overflow|Overflows]] are features of inline facilities and convey larger storm events out of the LID feature.<br> |
|
| |
|
| Construction Steps:<br> | | '''Construction Steps:'''<br> |
| #Connect the overflow drain to the underdrain. | | #Connect the overflow drain to the underdrain. |
| #Install overflow pit to grade at the location specified in the contract documents. | | #Install overflow pit to grade at the location specified in the contract documents. |
| #Fit a metal, domed grate to the overflow.<br> | | #Fit a metal, domed grate to the overflow.<br> |
|
| |
|
| Key Inspection Points:<br> | | '''Key Inspection Points:'''<br> |
| *Overflow drain matches design specifications. | | *Overflow drain matches design specifications. |
| *Overflow pit is positioned at the maximum water surface elevation of the practice, as per the contract documents. | | *Overflow pit is positioned at the maximum water surface elevation of the practice, as per the contract documents. |
Line 13: |
Line 13: |
| *Overflow grates located in high-traffic areas are screwed on or equipped with locks.<br> | | *Overflow grates located in high-traffic areas are screwed on or equipped with locks.<br> |
|
| |
|
| Mistakes to Avoid:<br> | | '''Mistakes to Avoid:'''<br> |
| *Backflows – ensure that backflows are avoided by confirming that inlet and overflow elevations match design specifications with surveys. | | *Backflows – ensure that backflows are avoided by confirming that inlet and overflow elevations match design specifications with surveys. |
| *Incorrect sequencing – install overflow drain prior to backfilling with granular material and engineered soil. | | *Incorrect sequencing – install overflow drain prior to backfilling with granular material and engineered soil. |