| ===Modular system=== | | ===Modular system=== |
| | #Sweep and blow the roof membrane clear and free of dirt, debris, and any sharp objects (such as flash clippings) |
| | #Inspect the waterproof membrane for any potential damage prior to installing root barrier |
| | #Install green roof perimeter or vegetation free zones (if applicable) a minimum 2 feet from parapet wall and around other critical infrastructure such as vents or roof drains |
| | #Install the root barrier (if applicable) on top of the roof membrane. |
| | ##Ensure sheet is goes up the parapet wall the full height of the green roof system (if applicable). |
| | ##Where additional root barrier sheets are laid side by side, a minimum of 30 cm overlap between sheets is needed. |
| | ##Make appropriate slits in root barrier with a retractable knife (away from existing waterproof membrane) to allow installation around roof infrastructure such as drains, air vents and stacks |
| | ##Please note that modular systems often include a root barrier built into the system but some systems recommend doubling up |
| | #Install the modular system according to manufacturer specifications or green roof design |
| | #If modular system is installed on a slope roof, the system will need to be anchored according to manufacturer specifications or design |
| | #Install irrigation system installation (if applicable) according to manufacturer specifications or design |
| | #Backfill vegetation free zones with clear stone (if applicable) |
|
| |
|
| ===Layered system=== | | ===Layered system=== |