| [[Underdrains]] are perforated pipes that collect subsurface water and convey water out of an LID facility once it reaches capacity. Their design is determined by the drainage requirements of the feature.
| |
|
| |
| '''Construction Steps:'''
| |
| #Install the underdrain to grade with a consistent slope of 0.5% to 1.0%.
| |
| #Connect overflow risers with single-elbowed ‘y’ connections or 45° elbows.
| |
| #Situate maintenance risers where siltation is expected in drain lines (such as at junctions or where grade and direction changes occur), in accordance with the design drawings.
| |
| #Mark the locations of risers.
| |
| #Use video inspections to confirm that the interior of the underdrain remains free of debris after construction.
| |
|
| |
| '''Key Inspection Points:'''
| |
| *Size, type, and material of the underdrain conforms to the design specifications.
| |
| *Underdrain is perforated prior to arrival on-site.
| |
| *Drain material is resistant to UV radiation and any chemicals in the soil and groundwater.
| |
| *Clean-outs are positioned correctly and spaced appropriately for the size of the underdrain.
| |
| *Any manual perforations are approved by the design or field engineer.
| |
| *Pipe grade matches design specifications.
| |
| *Tie-in locations to municipal sewers meet municipal specifications.
| |
|
| |
| '''Mistakes to Avoid:'''
| |
| *Incorrect overflow risers – ensure single-elbowed ‘y’ connections or 45° elbows are used for overflow risers instead of ‘T’ connections.
| |
| *Incorrect drain size – confirm underdrain has an internal diameter greater than or equal to 200 mm to reduce freezing and allow cleaning and camera inspections.
| |
| *Potential for clogging – Remove sock from underdrain prior to installation or geofabric wrap. A choker course is recommended, instead, as field change.
| |
|
| |
| For more information on the design of underdrains, such as materials and connections, see the page on underdrains linked above.
| |
|
| |
|
| ==Impermeable liners== | | ==Impermeable liners== |