Difference between revisions of "Excavation and grading"

From LID SWM Planning and Design Guide
Jump to navigation Jump to search
m
 
(6 intermediate revisions by the same user not shown)
Line 12: Line 12:


Clearing and grubbing is the stripping of vegetation and topsoil prior to excavation and rough grading within designated areas.
Clearing and grubbing is the stripping of vegetation and topsoil prior to excavation and rough grading within designated areas.
[[File:Scarification.JPG|400px|thumb|right|Scarifying native soils helps to increase infiltration rates. (Photo source: CVC)]]
[[File:Scarification.JPG|400px|thumb|right|Scarifying native soils helps to increase infiltration rates. (Photo source: CVC, 2022)]]
'''Construction steps'''  
'''Construction steps'''  
#Clear trees, large shrubs, stumps, etc. (grubbing).
#Clear trees, large shrubs, stumps, etc. (grubbing).
Line 32: Line 32:


Excavation to the specified depths in the drawings is critical to the LID feature’s future performance. It also requires heavy machinery which, if used incorrectly, can compact soils and lower their native infiltration rates. <br/>
Excavation to the specified depths in the drawings is critical to the LID feature’s future performance. It also requires heavy machinery which, if used incorrectly, can compact soils and lower their native infiltration rates. <br/>
[[File:Excavation outside in 2.JPG|400px|thumb|Excavating from impervious surfaces adjacent to the LID practice minimizes compaction.|right]]
[[File:Excavation outside in 2.JPG|400px|thumb|right|Excavating from impervious surfaces adjacent to the LID practice minimizes compaction. (Photo Source: CVC, 2018)]]
'''Construction steps'''
'''Construction steps'''
#Mark out the limit of excavation.
#Mark out the limit of excavation.
Line 46: Line 46:
*Confirm the limit of excavation.
*Confirm the limit of excavation.
*Use of excavation equipment specified in the contract, in the required manner (from the outside in, with a mini excavator, etc.).
*Use of excavation equipment specified in the contract, in the required manner (from the outside in, with a mini excavator, etc.).
*Confirm excavated rough grade and final grade prior to backfilling using survey equipment
*Confirm excavated rough grade and final grade prior to backfilling using survey equipment.
*Use of toothed bucket and scouring the bottom of practice if applicable
*Use of toothed bucket and scouring the bottom of practice if applicable.
*If appropriate, measure compaction using a cone penetration test or a cone penetrometer  
*If appropriate, measure compaction using a cone penetration test or a cone penetrometer .
*If appropriate, field verify infiltration rates at excavated bottom of practice using Guelph permeameter or double ring infiltrometer
*If appropriate, field verify infiltration rates at excavated bottom of practice using Guelph permeameter or double ring infiltrometer.
'''Mistakes to avoid:'''
'''Mistakes to avoid:'''
*making too many passes with heavy machinery within the LID footprint.
*Making too many passes with heavy machinery within the LID footprint.
*leaving heavy machinery within the LID’s footprint (for breaks, lunch, overnight, etc.)
*Leaving heavy machinery within the LID’s footprint (for breaks, lunch, overnight, etc.).
*using the wrong equipment
*Using the wrong equipment.
*over excavating
*Over excavating.
*smearing the bottom of the practice with the bucket, which can compact native soils
*Smearing the bottom of the practice with the bucket, which can compact native soils.


==Final excavated grade and verification==
==Final excavated grade and verification==
Line 61: Line 61:
LID designs typically have specific grading requirements. Verifying depths and slopes is critical for the optimal performance of the facility. For example, if the design calls for a channel with a 1% slope, the channel may not function as designed if it has a 2% slope instead.  
LID designs typically have specific grading requirements. Verifying depths and slopes is critical for the optimal performance of the facility. For example, if the design calls for a channel with a 1% slope, the channel may not function as designed if it has a 2% slope instead.  


[[File:trimble unit.JPG|400px|thumb|right|Always confirm elevations throughout construction. (Photo source: CVC)]]
[[File:trimble unit.JPG|400px|thumb|right|Always confirm elevations throughout construction. (Photo source: CVC, 2022)]]


Excavation to the sub-grade will differ depending on whether the design is for a [[Bioretention: Variations|full infiltration, partial infiltration, or no infiltration LID system]]. If it’s a full infiltration or partial infiltration practice, the sub-grade should be as level as possible to promote even infiltration across the facility’s footprint.  For no infiltration designs,  excavate sub-grade slopes to the design grade in the direction of the underdrain, typically 1 to 2%.  
Excavation to the sub-grade will differ depending on whether the design is for a [[Bioretention: Variations|full infiltration, partial infiltration, or no infiltration LID system]]. If it’s a full infiltration or partial infiltration practice, the sub-grade should be as level as possible to promote even infiltration across the facility’s footprint.  For no infiltration designs,  excavate sub-grade slopes to the design grade in the direction of the underdrain, typically 1 to 2%.  
Line 73: Line 73:
*Confirm final excavated depths and slopes.
*Confirm final excavated depths and slopes.
'''Mistakes to avoid'''
'''Mistakes to avoid'''
*“eye-balling” depths and slopes
*“Eye-balling” depths and slopes

Latest revision as of 21:34, 22 September 2022

The five-step construction process for sub-surface and ground-level LIDs.

The construction guidance in this section applies to all sub-surface and ground-level LID practices: bioretention gardens, bioswales, rain gardens, exfiltration trenches, enhanced swales, permeable pavements, infiltration trenches, infiltration chambers, and soakaways.

Overview[edit]

This section gives guidance for project managers, engineers, and contractors on the excavation and grading steps required for successful construction of sub-surface and ground-level LID practices.

Clearing and grubbing[edit]

Clearing and grubbing is the stripping of vegetation and topsoil prior to excavation and rough grading within designated areas.

Scarifying native soils helps to increase infiltration rates. (Photo source: CVC, 2022)

Construction steps

  1. Clear trees, large shrubs, stumps, etc. (grubbing).
  2. Use appropriately sized machinery (e.g. a mini-excavator) to strip sod and ground-level vegetation (clearing).
  3. Stockpile materials within designated areas if necessary. If the materials are being hauled offsite, stripped materials ideally would go straight into the back of a dump truck.
  4. Secure stockpiles with appropriate erosion and sediment control (ESC) measures if the material must be stored before hauling offsite or will be reused.

Key inspection points

  • Structural ESC measures are in place before clearing and grubbing begin.
  • Natural heritage features, including trees, and construction limits are clearly marked and respected by the contractor.
  • Contractor cleared and grubbed only within designated areas and according to the phasing plan.

Mistakes to avoid

  • clearing more area than is needed
  • insufficient marking of areas to be protected
  • stockpiling materials without ESC controls or for extended periods of time
  • leaving heavy equipment in the facility’s footprint
  • making excessive passes with heavy equipment in the LID practice’s footprint without scouring soil afterward

Excavation and rough grade[edit]

Excavation to the specified depths in the drawings is critical to the LID feature’s future performance. It also requires heavy machinery which, if used incorrectly, can compact soils and lower their native infiltration rates.

Excavating from impervious surfaces adjacent to the LID practice minimizes compaction. (Photo Source: CVC, 2018)

Construction steps

  1. Mark out the limit of excavation.
  2. Use predefined access routes to move heavy equipment.
  3. Cut and stabilize access and staging areas.
  4. Cut and stabilize channels and slopes.
  5. Excavate the LID feature from the outside-in whenever possible. A standard excavator (10-45 tons) has a longer reach than mini (<6 tons) or midi excavators (6-10 tons) and can be the best choice despite its weight, since it may not need to enter into the facility’s footprint to complete the job. However, a mini excavator would be the best choice if entry into the LID feature’s footprint is necessary.
  6. Excavate to within 100 mm of the final grade.
  7. Check grades with appropriate equipment (transit levels, etc.).
  8. Stockpile materials in a designated area if it must be stored before hauling.

Key inspection points:

  • Confirm the limit of excavation.
  • Use of excavation equipment specified in the contract, in the required manner (from the outside in, with a mini excavator, etc.).
  • Confirm excavated rough grade and final grade prior to backfilling using survey equipment.
  • Use of toothed bucket and scouring the bottom of practice if applicable.
  • If appropriate, measure compaction using a cone penetration test or a cone penetrometer .
  • If appropriate, field verify infiltration rates at excavated bottom of practice using Guelph permeameter or double ring infiltrometer.

Mistakes to avoid:

  • Making too many passes with heavy machinery within the LID footprint.
  • Leaving heavy machinery within the LID’s footprint (for breaks, lunch, overnight, etc.).
  • Using the wrong equipment.
  • Over excavating.
  • Smearing the bottom of the practice with the bucket, which can compact native soils.

Final excavated grade and verification[edit]

LID designs typically have specific grading requirements. Verifying depths and slopes is critical for the optimal performance of the facility. For example, if the design calls for a channel with a 1% slope, the channel may not function as designed if it has a 2% slope instead.

Always confirm elevations throughout construction. (Photo source: CVC, 2022)

Excavation to the sub-grade will differ depending on whether the design is for a full infiltration, partial infiltration, or no infiltration LID system. If it’s a full infiltration or partial infiltration practice, the sub-grade should be as level as possible to promote even infiltration across the facility’s footprint. For no infiltration designs, excavate sub-grade slopes to the design grade in the direction of the underdrain, typically 1 to 2%.

As with all infiltrating LID practices, avoid compaction of sub-grade soils whenever possible. However, depending on the design and the local municipality, compaction of the sub-grade may be required for permeable pavement LIDs.

Construction steps

  1. Excavate the final 100 mm, to the final design grade, using appropriate equipment. This is often done with hand tools.
  2. Confirm excavation depths and slopes using appropriate equipment (transit levels, global navigation satellite systems, etc.)

Key inspection points

  • Confirm final excavated depths and slopes.

Mistakes to avoid

  • “Eye-balling” depths and slopes